Question

An investment project is accepted if its NPV is less than its WACC. True False

  1. An investment project is accepted if its NPV is less than its WACC.

    True

    False

Homework Answers

Answer #1

If net present value is less than weighted average cost of capital, it will mean that the company is not able to to exceed the hurdle rate and it is not able to recover the cost of the capital from the net present value of the project so if the net present value is not higher than weighted average cost of capital, it will mean that a project is not yielding with the the required benefits to the company and it should not be accepted.

Generally there is a a trend of comparison of internal rate of return with weighted average cost of capital.

So, the given statement is FALSE.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less...
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less than 1; greater than 1 Less than 0; greater than 0 Greater than 1; less than 1 Greater than 0; less than 0 Equal to 1; Greater than 1 Equal to 0; Greater than 0
Calculate the NPV and explain if the project should be accepted if the WACC is 10%...
Calculate the NPV and explain if the project should be accepted if the WACC is 10% and the initial investment is $35,000. Cash flows for years 1 through 3 are: $20,000; ($15,000) and $12,000. Why would you not use the IRR method to evaluate this project?
Which one of the following indicates a project should be accepted? A. NPV < 0 B....
Which one of the following indicates a project should be accepted? A. NPV < 0 B. IRR>WACC C. IRR<WACC D. NPV=1
16. If a company's WACC is 10%, which of the following projects will be accepted? Select...
16. If a company's WACC is 10%, which of the following projects will be accepted? Select all that apply: IRR = 8% MIRR = 12% NPV = $100,000 MIRR = 9% 14. As interest rates go up, which of the following is true? Select all that apply: Bond Prices go down. The NPV of a project goes down. The NPV of a project goes up. The NPV of a short term project goes down quicker than the NPV of a...
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR...
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR that is greater than the discount rate if the proposed capital budgeting projects are independent. 1(b). (TRUE or FALSE?) Projects with NPVs of positive values will reduce the firm’s value but it just meet the firm’s requirements.
Apply WACC in NPV.  Brawn Blenders has the following incremental cash flow for its new​ project:...
Apply WACC in NPV.  Brawn Blenders has the following incremental cash flow for its new​ project: Category T0 T1 T2 T3 Investment -$3,251,000 * * * Net_working_capital_change -$225,000 * * $225,000 Operating_cash_flow * $1,158,000 $1,158,000 $1,158,000 Salvage * * * $268,000 Should Brawn accept or reject this project at an adjusted WACC of 11.07​%, 13.07​%, or 15.07​%?
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater...
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater than WACC; less than WACC Greater than MIRR; less than MIRR Less than WACC; greater than WACC Less than MIRR; greater than MIRR Less than 0; Greater than 0 Greater than 0; Less than 0
1. NPV According to the text, the NPV rule states that "An investment should be accepted...
1. NPV According to the text, the NPV rule states that "An investment should be accepted if the NPV is positive and rejected if it is negative." What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV (or very close to zero) what would you do? Why? 2. FORECASTING ERROR (RISK) What is a "forecasting error"? Why is it important to the analysis of capital expenditure projects? please, original work.
The NPV rule states that, “An investment should be accepted if the net present value (...
The NPV rule states that, “An investment should be accepted if the net present value ( NPV) is positive and rejected if it is negative.” What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV ( or very close to zero) what would you do? Why?