Question

Which one of the following indicates a project should be accepted? A. NPV < 0 B....

Which one of the following indicates a project should be accepted?

A. NPV < 0

B. IRR>WACC

C. IRR<WACC

D. NPV=1

Homework Answers

Answer #1

Correct statement is B

--------------------------------------------------------------------------------------------------------------------------

IRR is the internal rate on the investment.

WACC is weighted cost of capital, for project to be accepted, IRR must be greater than WACC.

--------------------------------------------------------------------------------------------------------------------------

Feel free to comment if you need further assistance J

Pls rate this answer if you found it useful.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Calculate the NPV and explain if the project should be accepted if the WACC is 10%...
Calculate the NPV and explain if the project should be accepted if the WACC is 10% and the initial investment is $35,000. Cash flows for years 1 through 3 are: $20,000; ($15,000) and $12,000. Why would you not use the IRR method to evaluate this project?
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of return is 16%. Use this information for the next 3 questions. Year Project A Cash Flow Project B Cash Flow 0 ($50,000) ($20,000) 1 15,000 6,000 2 15,000 6,000 3 15,000 6,000 4 13,500 5,400 5 13,500 5,400 6 6,750 5,400 Which of the following statements is true concerning projects A and B? a) Due to time disparity, IRR indicates that project A should...
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less...
A project should be rejected if NPV is _____ and accepted if NPV is _____. Less than 1; greater than 1 Less than 0; greater than 0 Greater than 1; less than 1 Greater than 0; less than 0 Equal to 1; Greater than 1 Equal to 0; Greater than 0
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater...
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater than WACC; less than WACC Greater than MIRR; less than MIRR Less than WACC; greater than WACC Less than MIRR; greater than MIRR Less than 0; Greater than 0 Greater than 0; Less than 0
Assume the following: Project A NPV = $5,767 IRR = 18.2% Project B NPV = $2,398...
Assume the following: Project A NPV = $5,767 IRR = 18.2% Project B NPV = $2,398 IRR = 20.3% If projects were independent, which project(s) should be selected? Group of answer choices Select project B only Select project A only Both projects would be selected
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
1(a). When NPV less than 0, then: Select one: a. IRR=0 b. IRR greater than required...
1(a). When NPV less than 0, then: Select one: a. IRR=0 b. IRR greater than required return c. IRR less than 0 d. IRR less than 0 e. IRR less than required return 1(b). When IRR greater than required return, then: Select one: a. NPV greater than 0 b. NPV less than required return c. NPV greater than required return d. NPV=0 e. NPV less than 0
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT