Question

A firm wants to start a project. A team of financial analysts estimated the following cash...

A firm wants to start a project. A team of financial analysts estimated the following cash flows

year                  cash flow

0 -$100,000

1 55,000

2 43,000

3 45,000

Suppose that the discount rate (interest rate) is 12%. The NPV is

Homework Answers

Answer #1

Net present value can be solved using a financial calculator. The steps to solve on the financial calculator:

  • Press the CF button.
  • CF0= -$100,000. Indicate the initial cash flow by a negative sign since it is a cash outflow.  
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the NPV button and enter the discount rate of 12%.
  • Press enter after that. Press the down arrow and CPT buttons to get the net present value.  

Net present value at 12% discount rate is $15,416.59.

In case of any query, kindly comment on the solution.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
What is the equivalent annual annuity for a 4-yr project with the following cash flows and...
What is the equivalent annual annuity for a 4-yr project with the following cash flows and a discount rate of 9%? Year Cash Flow 0 (175,000) 1 45,000 2 55,000 3 65,000 4 85,000 What is the payback period for a project with the following cash flows: Year Cash Flow 0 (175,000) 1 45,000 2 55,000 3 65,000 4 85,000 What is the net present value for a project with the following cash flows and a discount rate of 9%?...
Risky Business is looking at a project with the following estimated cash​ flow: Risky Business wants...
Risky Business is looking at a project with the following estimated cash​ flow: Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate for the project is 8​%.   If the cutoff period is 6 years for major​ projects, determine whether the management at Risky Business will accept or reject the project under the five different decision models. Initial investment at start of project   13,500,000 Cash flow at end of year...
Suppose your firm is considering investing in a project with the cash flows shown as follows,...
Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the project are three and three and a half years, respectively. . Time                          0                               1                                2                                         3                              4                                            5 Cash Flow             -100,000                   30,000                       45,000                                 55,000                     30,000                                  10,000 Use the IRR decision rule to evaluate this project; should it be...
Suppose your firm is considering investing in a project with the cash flows shown as follows,...
Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the project are three and three and a half years, respectively Time                                    0                     1             2                          3                4                                5 Cash Flow                        -100,000        30,000        45,000            55,000          30,000                    10,000 Calculate the payback and use the payback decision rule...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$11,700,000 Cash flow at end of year​ one: ​$2,106,000 Cash flow at end of years two through​ six: ​$2,340,000 each year Cash flow at end of years seven through​ nine: ​$2,527,200 each year Cash flow at end of year​ ten: ​$1,805,143 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate...
You've estimated the following cash flows (in $) for a project: The required return is 8.5%....
You've estimated the following cash flows (in $) for a project: The required return is 8.5%. What is the IRR for the project? What is the NPV of the project? A B 1 Year Cash flow 2 0 -3,320 3 1 974 4 2 1,281 5 3 1,875
Comparing all methods. Risky Business is looking at a project with the estimated cash flow as?...
Comparing all methods. Risky Business is looking at a project with the estimated cash flow as? follows: Initial investment at start of? project:?? ?$10,900,00 Cash flow at end of year? one:?? ?$1,853, 000 Cash flow at end of years two through? six:?? ?$2,180,000 each year Cash flow at end of years seven through? nine:?? ?$2,408, 900, each year Cash flow at end of year? ten:?? ?$1,853,000 Risky Business wants to know the payback? period, NPV,? IRR, and PI of this...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$13,000,000 Cash flow at end of year​ one: $2,080,000 Cash flow at end of years two through​ six: $2,600,000 each year Cash flow at end of years seven through​ nine: $2,496,000 each year Cash flow at end of year​ ten: $1,920,000 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate...
10.       Suppose a firm is interested in purchasing the following income producing property at a current...
10.       Suppose a firm is interested in purchasing the following income producing property at a current market price of $450,000. The prospective buyer has estimated the expected cash flows over the next four years to be as follows: Year 1 = $40,000, Year 2 = $45,000, Year 3 = $50,000, Year 4 = $55,000. Assuming that the required rate of return is 12% and the estimated proceeds from selling the property at the end of year four is $500,000, what...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT