Question

You've estimated the following cash flows (in $) for a project: The required return is 8.5%....

You've estimated the following cash flows (in $) for a project:

The required return is 8.5%.

What is the IRR for the project?

What is the NPV of the project?

A B
1 Year Cash flow
2 0 -3,320
3 1 974
4 2 1,281
5 3 1,875

Homework Answers

Answer #1

NPV 134

IRR 10.504%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year...
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,200 3 1 974 4 2 1,281 5 3 1,647 The required return is 8.5%. Attempt 1/1 for 10 pts. Part 1 What is the IRR for the project? Submit Attempt 1/1 for 10 pts. Part 2 What is the NPV of the project? Submit Attempt 1/1 for 10 pts. Part 3 What should you do? Check all that apply:...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -5,400 3 1 1,325 4 2 2,148 5 3 2,258    Attempt 3/10 for 6 pts. Part 1 What is the IRR for the project?
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...
You've estimated the following cash flows (in $) for two projects: Year Project A Project B...
You've estimated the following cash flows (in $) for two projects: Year Project A Project B 0 -5,100 -7,650 1 1,325 1,325 2 2,148 2,148 3 3,444 6,967 The required return for both projects is 8%. What is the NPV for project A? What is the NPV for project B? Which project seems better according to the NPV method? Project A or Project B
You've estimated the following cash flows (in $) for two projects: Year Project A Project B...
You've estimated the following cash flows (in $) for two projects: Year Project A Project B 0 -5,400 -8,100 1 1,325 1,325 2 2,148 2,148 3 3,942 7,751 The required return for both projects is 8%. A:What is the NPV for project A? B:What is the NPV for project B? C:Which project seems better according to the NPV method?
Intro You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project...
Intro You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,500 -8,250 1 1,325 1,325 2 2,148 2,148 3 4,010 7,918 The required return for both projects is 8%.    Attempt 1/10 for 10 pts. Part 1 What is the IRR for project A? Submit    Attempt 1/10 for 10 pts. Part 2 What is the IRR for project B? Submit    Attempt 1/5 for 10 pts. Part 3 Which project seems better...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37004 $11550 $12750 $16800 $10700 $5350 NPV=4947. IRR=18.0% NPV=4947. IRR=9.9% NPV=9464. IRR=9.9% NPV=9464. IRR=18.0%
Carland, Inc., has a project available with the following cash flows. If the required return for...
Carland, Inc., has a project available with the following cash flows. If the required return for the project is 8.1 percent, what is the project's NPV? Year Cash Flow 0 −$260,000 1 68,700 2   92,600 3   118,800 4 71,700 5 −12,200 Multiple Choice $29,347.72 $15,004.25 $37,612.50 $17,147.72 $21,082.94
The following table shows the cash flows for a project. The required rate of return in...
The following table shows the cash flows for a project. The required rate of return in 20%. Compute the IRR. Year Project cash flow 0 -$120,000 1 $100,000 2 $40,000 3 $10,000 Group of answer choices 17% 20% 18% 19%