Question

You are considering the following two projects and can take only one. Your cost of capital...

You are considering the following two projects and can take only one. Your cost of capital is 11.0%.

The cash flows for the two projects are as follows​ ($ million):

Project

Year 0

Year 1

Year 2

Year 3

Year 4

A

−$100

$25

$30

$40

$50

B

−$100

$50

$40

$30

$20

a. What is the IRR of each​ project?

b. What is the NPV of each project at your cost of​ capital?

c. At what cost of capital are you indifferent between the two​ projects?

d. What should you​ do?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering the following two projects and can take only one. Your cost of capital...
You are considering the following two projects and can take only one. Your cost of capital is 11.9%. The cash flows for the two projects are as follows​ ($ million): Project   Year 0   Year 1   Year 2   Year 3   Year 4   A -$103 28 34 44 53 B -$103 53 44 34 24 What is the IRR of each project? Which project should you choose? Select one: a. IRR of Project A = 11.9%, IRR of Project B = 17.7%....
You are considering the following two projects and can take only one. Your cost of capital...
You are considering the following two projects and can take only one. Your cost of capital is 8%. The cash flows are as follow: Year 0 1 2 3 4 A -1000 300 500 300 300 B -1000 400 100 500 500 Which one do you choose? A. Project B B. None of them. C. Project A.
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A: - $50 $25 $22 $19 $13 B: - $98 $21 $41 $50 $62 a. What are the IRRs of the two​ projects? - The IRR for project A is ? - The IRR for project B is ? b. If your discount rate is 5.1 %​, what are...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A: - $49   $23 $19 $22 $17 B: - $102 $20 $40 $48 $60 a. What are the IRRs of the two​ projects? - The IRR for project A is ? - The IRR for project B is ? b. If your discount rate is 5.5 %​, what are...
You have two potential investment projects, Project A and Project B. You can take one, but...
You have two potential investment projects, Project A and Project B. You can take one, but not both. The annual cash flows for the two projects are: Year 0 1 2 3 Project A Cash Flow -$50,000 $45,000 $5,000 $5,000 (respectively) Project B Cash Flow -$50,000 $5,000 $5,000 $50,000 (respectively). a) Compute the IRR for each project. b) Compute the NPV for each project if the appropriate discount rate is 5%. Which project would you take, and why? c) Compute...
19. Your division is considering two investment projects, each of which requires an up-front expenditure of...
19. Your division is considering two investment projects, each of which requires an up-front expenditure of $24 million. You estimate that the cost of capital is 12% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two decimal places. Project A: _years...
Homework - Capital Budgeting 1.The Hyatt Group Inc., has identified the following two mutually exclusive projects:...
Homework - Capital Budgeting 1.The Hyatt Group Inc., has identified the following two mutually exclusive projects: ​Cash Flows​Cash Flows Year​Project A​Project B 0​-$10,000​_$10,000 1​ 200​ 5,000 2​ 500​ 6,000 3​ 8,200​ 500 4​ 4,800​ 500 a. What is the IRR of each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required rate of return is 9 percent, what is the NPV of each of...
You have to choose one project. Cost of Capital is 11% 0                      1          &nbs
You have to choose one project. Cost of Capital is 11% 0                      1                      2                      3                      4 ___________________________________________________________________ A                     -100                 25                    30                    40                    50             B                     -100                 50                    40                    30                    20 How much is the superior project’s proper metric (NPV or IRR? And how much is it?) Choice criteria is equal to  __________ (NPV number, or IRR%)
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$48 $26 $21 $21 $$13 B −$100 $22 $40 $51 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.1%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
7. Your division is considering two investment projects, each of which requires an up-front expenditure of...
7. Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $__ Project B: $__ What are...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT