Question

You are considering the following two projects and can take only one. Your cost of capital...

You are considering the following two projects and can take only one. Your cost of capital is 8%. The cash flows are as follow:

  1. Year

    0

    1

    2

    3

    4

    A

    -1000

    300

    500

    300

    300

    B

    -1000

    400

    100

    500

    500

    Which one do you choose?

    A.

    Project B

    B.

    None of them.

    C.

    Project A.

Homework Answers

Answer #1

A:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=300/1.08+500/1.08^2+300/1.08^3+300/1.08^4

=1165.11

NPV=Present value of inflows-Present value of outflows

=1165.11-1000

=$165.11(Approx)

B:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=400/1.08+100/1.08^2+500/1.08^3+500/1.08^4

=1220.54

NPV=Present value of inflows-Present value of outflows

=1220.54-1000

=$220.54(Approx).

Hence B must be selected having higher NPV

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are considering the following two projects and can take only one. Your cost of capital...
You are considering the following two projects and can take only one. Your cost of capital is 11.0%. The cash flows for the two projects are as follows​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$100 $25 $30 $40 $50 B −$100 $50 $40 $30 $20 a. What is the IRR of each​ project? b. What is the NPV of each project at your cost of​ capital? c. At what cost of capital...
You are considering the following two projects and can take only one. Your cost of capital...
You are considering the following two projects and can take only one. Your cost of capital is 11.9%. The cash flows for the two projects are as follows​ ($ million): Project   Year 0   Year 1   Year 2   Year 3   Year 4   A -$103 28 34 44 53 B -$103 53 44 34 24 What is the IRR of each project? Which project should you choose? Select one: a. IRR of Project A = 11.9%, IRR of Project B = 17.7%....
You are considering the following project. Your cost of capital is 8%. The cash flows are...
You are considering the following project. Your cost of capital is 8%. The cash flows are as follow: Year 0 1 2 3 4 -1000 400 100 500 500 What is the NPV of this project? A. 389 B. 221 C. 500 D. 1500
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been...
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 0 1 2 3 4 Project A -1,350 650...
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
Cowboy Corp. is about to expand its operations and they have several projects with various cash...
Cowboy Corp. is about to expand its operations and they have several projects with various cash flows available in Excel upload file. Each project has an 8-year life and the firm has a cost of capital at 8%. The firm has $15,000 for the expansion and will invest in multiple projects with that capital constraint. 1. Calculate NPV for each project 2. Find the project combination that maximizes total NPV for Cowboy Corp. and calculate total capital spending 3. Find...
Patterson Co. is considering a project that has the following cash flow and cost of capital...
Patterson Co. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected. r. 10.00% Year 0 1 2 3 Cash flows −$950 $500 $400 $300
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been...
Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 0 1 2 3 4 Project A -920 700...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are 2.5 and 3.5 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -1,000 300 400 700   Project B Cash Flow -500 200 400 300 Use the payback decision rule to evaluate these projects;...