You are considering the following two projects and can take only one. Your cost of capital is 8%. The cash flows are as follow:
Year |
0 |
1 |
2 |
3 |
4 |
A |
-1000 |
300 |
500 |
300 |
300 |
B |
-1000 |
400 |
100 |
500 |
500 |
Which one do you choose?
A. |
Project B |
|
B. |
None of them. |
|
C. |
Project A. |
A:
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=300/1.08+500/1.08^2+300/1.08^3+300/1.08^4
=1165.11
NPV=Present value of inflows-Present value of outflows
=1165.11-1000
=$165.11(Approx)
B:
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=400/1.08+100/1.08^2+500/1.08^3+500/1.08^4
=1220.54
NPV=Present value of inflows-Present value of outflows
=1220.54-1000
=$220.54(Approx).
Hence B must be selected having higher NPV