Question

7. Your division is considering two investment projects, each of which requires an up-front expenditure of...

7. Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows:

Year

Project A

Project B

1

$ 4,000,000

$20,000,000

2

10,000,000

10,000,000

3

20,000,000

6,000,000

  1. What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar.

Project A: $__

Project B: $__

What are the two projects' net present values, assuming the cost of capital is 10%? Do not round intermediate calculations. Round your answers to the nearest dollar.

Project A: $__

Project B: $__  

What are the two projects' net present values, assuming the cost of capital is 15%? Do not round intermediate calculations. Round your answers to the nearest dollar.

Project A: $__

Project B: $__

  1. What are the two projects' IRRs at these same costs of capital? Do not round intermediate calculations. Round your answers to two decimal places.

Project A:    __ %

Project B:    __%

8. Edelman Engineering is considering including two pieces of equipment, a truck, and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000, and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows:

Year

Truck

Pulley

1

$5,100

$7,500

2

5,100

7,500

3

5,100

7,500

4

5,100

7,500

5

5,100

7,500

Calculate the IRR, the NPV, and the MIRR for each project, and indicate the correct accept/reject decision for each. Do not round intermediate calculations. Round the monetary values to the nearest dollar and percentage values to two decimal places. Use a minus sign to enter negative values, if any.

Truck

Pulley

Value

Decision

Value

Decision

IRR

__%

(select one) Accept/Reject

__ %

(select one)Accept/Reject

NPV

      $__           

(select one) Accept/Reject

     $ __         

(select one) Accept/Reject

MIRR

        __%

(select one) Accept/Reject

__%

(select one)Accept/Reject

Homework Answers

Answer #1

7 a) At the cost of capital of 5%

NPV of A (in million $) = -17+ 4/1.05+10/1.05^2+20/1.05^3

=$13.15657056 million

or $13,156,571

NPV of B (in million $) = -17+ 20/1.05+10/1.05^2+6/1.05^3

=$16.3009394 million

or $16,300,939

At the cost of capital of 10%

NPV of A (in million $) = -17+ 4/1.1+10/1.1^2+20/1.1^3

=$9.927122 million

or $9,927,122

NPV of B (in million $) = -17+ 20/1.1+10/1.1^2+6/1.1^3

=$13.954170 million

or $13,954,170

At the cost of capital of 15%

NPV of A (in million $) = -17+ 4/1.15+10/1.15^2+20/1.15^3

=$7.190022 million

or $7,190,022

NPV of B (in million $) = -17+ 20/1.15+10/1.15^2+6/1.15^3

=$11.897838 million

or $11,897,838

IRR is the discount rate at which NPV =0

IRR (r) of project A is given by

-17+4/(1+r)+10/(1+r)^2+20/(1+r)^3 = 0

From SOLVER in excel OR by using hit and trial method,

r = 0.3354 or 33.54%

IRR of project A = 33.54%

IRR (r) of project B is given by

-17+20/(1+r)+10/(1+r)^2+6/(1+r)^3 = 0

From SOLVER in excel OR by using hit and trial method,

r = 0.6592 or 65.92%

IRR of project B = 65.92%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Your division is considering two investment projects, each of which requires an up-front expenditure of $15...
Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $    Project B: $    What are the two...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the two...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17...
Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the two...
Your division is considering two investment projects, each of which requires an up-front expenditure of $15...
Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the two...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $19,000 and that for the pulley system is $20,000. The firm's cost of capital is 12%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $23 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 8,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ 8,107,500 Project B $ 12,026,400 What are the two projects' net...
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system,...
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100 7,500 Calculate the IRR for each project....
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system,...
Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $19,000 and that for the pulley system is $20,000. The firm's cost of capital is 12%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100 7,500 Calculate the IRR for each project....
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment,...
NPVs, IRRs, and MIRRs for Independent Projects Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $15,000, and that for the pulley system is $21,000. The firm's cost of capital is 11%. After-tax cash flows, including depreciation, are as follows: Year Truck Pulley 1 $5,100 $7,500 2 5,100 7,500 3 5,100 7,500 4 5,100 7,500 5 5,100...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT