You have two potential investment projects, Project A and Project B. You can take one, but not both. The annual cash flows for the two projects are: Year 0 1 2 3 Project A Cash Flow -$50,000 $45,000 $5,000 $5,000 (respectively) Project B Cash Flow -$50,000 $5,000 $5,000 $50,000 (respectively). a) Compute the IRR for each project. b) Compute the NPV for each project if the appropriate discount rate is 5%. Which project would you take, and why? c) Compute the NPV for each project if the appropriate discount rate is 10%. Which project would you take, and why? d) Summarize the principles demonstrated by this problem.
a: IRR of A = 7.87%, IRR of B = 6.89%
b: NPV at 5% is higher for Project B hence that will be selected.
c: NPV at 10% is higher for A hence A will be selected.
Year | A | B |
0 | -50000 | -50000 |
1 | 45000 | 5000 |
2 | 5000 | 5000 |
3 | 5000 | 50000 |
IRR | 7.87% | 6.89% |
NPV | 1711.48 | 2488.93 |
NPV | -1202.10 | -3756.57 |
WORKINGS
Get Answers For Free
Most questions answered within 1 hours.