Question

When considering Cost-Plus Reimbursable contracts, Company X is negotiation between Cost-Plus-Percentage-of-Costs or Cost-Plus-Fixed Fee. If the...

When considering Cost-Plus Reimbursable contracts, Company X is negotiation between Cost-Plus-Percentage-of-Costs or Cost-Plus-Fixed Fee. If the estimated costs were 4,500, and the percentage is 10%, and if the actual costs increased to $4,800 - which contract is better for the buyer. please explain

Homework Answers

Answer #1

In cost plus percentage of cost contract, buyer has to pay all the cost incured for the contract plus percentage of contract expense that was initially agreed upon where as in  Cost-Plus-Fixed Fee , buyer has to pay all the cost incured for the contract plus fixed fee initially agreed upon

Thus if estimated cost at time of signing contract was 4500$ and 10% was fixed , than estimated cost for buyer was 4500 $+ 10%(4500$)

= 4500$+450$

=4950$

now actual cost came to be 4800 $, thus buyer need to pay = $4800 + 10%($4800)

=$4800 + $480

= $5280

Thus extra cost to be incurred by buyer = $5280 - $4950 = 330$

Thus it is better for buyer to go for Cost-Plus-Fixed Fee as irrespective of cost incurred, fees will be fixed

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long...
Long Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Long began work on a $400 million fixed-fee construction contract, which was completed in 2024. Cost incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Cost Incurred Estimated Costs to Complete as of December 31 2021 $60 $240 2022 $84 $176 For the year 2022, Long should have recognized gross profit on this contract...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood began work on a $4,300,000 fixed-fee construction contract, which was completed in 2024. Cost Incurred Estimated Additional Cost to Complete 2021 $800,000 $3,200,000 2022 $1,000,000 $2,200,000 2023 $936,000 $1,064,000 For the year 2023, Redwood should have recognized gross profit on this contract of: A)500,000 B)300,000 C)225,00 D)135,000
Petra Company uses standard costs for cost control and internal reporting. Fixed costs are budgeted at...
Petra Company uses standard costs for cost control and internal reporting. Fixed costs are budgeted at $36,000 per month at a normal operating level of 10,000 units of production output. During October, actual fixed costs were $40,000, and actual production output was 12,000 units. Required a Determine the fixed overhead budget variance. b Assume that the company applied fixed overhead to production on a per-unit basis. Determine the fixed overhead volume variance. Was the fixed overhead budget variance from requirement...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $190,800 plus $13 per direct labour hour. The overhead rate is based on 10,600 hours. Actual results were: Standard direct labour hours allowed 9,070 Actual direct labour hours 10,600 Fixed overhead $179,000 Variable overhead $174,400 Calculate the fixed overhead production volume variance. Fixed overhead production volume variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate the variable overhead spending variance. Variable overhead spending variance $ Neither favourable nor unfavourableUnfavourableFavourable Calculate...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
A company that offers cars for rent wants to better understand costs. When cars are returned,...
A company that offers cars for rent wants to better understand costs. When cars are returned, they are thoroughly cleaned before being rented again. The manager believes that the variable portion of the cleaning costs relates to the number of rental returns. She has gathered the following data: Month Rental Returns Cleaning Costs January 2,500 $ 12,000 February 2,500 $ 13,600 March 2,800 $ 12,800 April 3,200 $ 15,800 May 3,700 $ 17,200 June 5,200 $ 25,300 July 5,600 $...
1. X Company uses account analysis to estimate total overhead costs for each month, with units...
1. X Company uses account analysis to estimate total overhead costs for each month, with units produced as the activity measure. In May, when production was 1,000 units, the plant manager classified each overhead cost item as fixed and variable as follows: Cost Item Total Cost Cost Behavior Utilities    $21,200   100% variable Supplies     23,100 60% variable Maintenance     20,000 100% fixed If September production is expected to be 1,180 units, what are estimated total overhead costs in September (round unit costs...
1.Alameda Instruments (AI) has offered to supply the Air Force with computer monitors at "cost plus...
1.Alameda Instruments (AI) has offered to supply the Air Force with computer monitors at "cost plus 20 percent." AI operates a manufacturing plant that can produce 22,000 monitors per year, but it normally produces 20,000. The costs to produce 20,000 monitors follow: Total Cost Cost per Monitor   Production costs:        Materials $ 1,340,000 $ 67        Labor 1,600,000 80        Supplies and other costs that will vary with production 880,000 44        Indirect cost that will not vary with production 680,000 34   Variable marketing...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
1) X Company incurred the following costs in 2017: Factory insurance $5,629 Customer service 4,766 Advertising...
1) X Company incurred the following costs in 2017: Factory insurance $5,629 Customer service 4,766 Advertising costs 4,594 Factory maintenance 5,023 Direct labor 5,972 Direct materials 4,514 Sales salaries 5,023 Factory utilities 5,153 Research & Development 5,599 Material handling 4,174 What was total overhead in 2017? 2) X Company had the following inventory account balances in 2017: Account January 1 December 31 Materials $14,524    $16,900      Work in Process 14,622    21,768      Finished Goods 14,594    14,594      The following additional information for the...