Question

The annual incremental cash flows from projects A and B are given below. Both projects have...

The annual incremental cash flows from projects A and B are given below. Both projects have the same discount rate. Using the logic of time value, which of the following is true as long as your discount rate is positive?

Project

Start of Year 1

Start of Year 2

Start of Year 3

Start of Year 4

Start of Year 5

Start of Year 6

A

100

100

100

-100

-100

-100

B

-100

-100

-100

100

100

100

  1. Project A is better than project B
  2. Project B is better than project A
  3. Projects A and B will be of equal value
  4. There is not enough information to answer this question.

Homework Answers

Answer #1

The future cash flows of both of the projects are same, but the timings of cash flows are different.

In project A, the larger cash flows occurs initially and it implies that the larger cash flows will be discounted by a higher present value factor.

In project B, the larger cash flows occurs later and it implies that the larger cash flows will be discounted by a lower present value factor.

Hence it is clearly implied that the project A will always be better than project B.

So, the correct answer is option a.

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You have two projects to consider. Both have 4-years of cash flows and a 4% discount...
You have two projects to consider. Both have 4-years of cash flows and a 4% discount rate is appropriate for both projects. The cash flows for project X have a present value of $362.99. Present Value @ 4% End of Year 1 End of Year 2 End of Year 3 End of Year 4 Project X 362.99 100 100 100 100 Project Y -100 -100 -100 -100 Which of the following is correct? You would accept project X if the...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions: year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 1)  Which project should be accepted, if any and why? A: Project B; it has a higher IRR and PI B: Neither project should be accepted, they both have negative NPVs C: Both project should be accepted; they have IRRs greater...
Two projects have the same initial cost. Project A has estimated cash flows of $1,000, $2,000,...
Two projects have the same initial cost. Project A has estimated cash flows of $1,000, $2,000, $3,000, $4,000 at the end of years 1 to 4 respectively. Project B has estimated cash flows of $4,000, $3,000, $2,000, $1,000 at the end of years 1 to 4 respectively. Which project will have the greater NPV assuming a positive discount rate? Select one: a. The NPV will be the same for both Project A and Project B b. Project B c. Project...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A: - $49   $23 $19 $22 $17 B: - $102 $20 $40 $48 $60 a. What are the IRRs of the two​ projects? - The IRR for project A is ? - The IRR for project B is ? b. If your discount rate is 5.5 %​, what are...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A: - $50 $25 $22 $19 $13 B: - $98 $21 $41 $50 $62 a. What are the IRRs of the two​ projects? - The IRR for project A is ? - The IRR for project B is ? b. If your discount rate is 5.1 %​, what are...
Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation.  Both projects...
Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation.  Both projects require an annual return of 15 percent.   As a financial analyst for thecompany, you are asked the following questions. a.If your decision rule is to accept the project with the greater IRR, which project should you choose? Explain why b.  Since you are fully aware of the IRR rule's scale problem, you calculate the incremental IRR for the cash flows.  Based on your computation, which project...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$48 $26 $21 $21 $$13 B −$100 $22 $40 $51 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.1%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
Morgan Corporation is trying to decide which one of two projects it should accept. Both projects...
Morgan Corporation is trying to decide which one of two projects it should accept. Both projects have the same start-up cost. Project 1 will produce annual cash flows of $52,000 a year for six years. Project 2 will produce cash flows of $48,000 a year for eight years. The company requires a 15 percent rate of return. Which project should the company select and why?
In projects with unconventional cash flows (negative and positive cash flows throughout the life of the...
In projects with unconventional cash flows (negative and positive cash flows throughout the life of the project), the phenomenon of multiple rates of return can occur. In these cases, the internal rate of return (IRR) is the most appropriate method of project evaluation. a. True b. False
"Potential projects A and B have the following cash flows. Use i = 13.4% annual rate...
"Potential projects A and B have the following cash flows. Use i = 13.4% annual rate compounded annually. Enter the Net Present Worth (NPW) of the preferred project. If neither project should be selected, enter 0. Project A Year 0: -$4,700 Year 1: $2,600 Year 2: $2,100 Year 3: $900 Project B Year 0: -$4,000 Year 1: $2,800 Year 2: $1,500 Year 3: $400"