Question

Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...

Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; answer the next 2 questions:

year Project A Project B
0 -5000 -1000
1 2500 600
2 2500 600
3 2500 600

1)  Which project should be accepted, if any and why?

A: Project B; it has a higher IRR and PI

B: Neither project should be accepted, they both have negative NPVs

C: Both project should be accepted; they have IRRs greater than the cost of capital

D: Project A; it has the higher positive NPV

E: Not enough information to answer.

Question 2:

Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital;

year Project A Project B
0 -5000 -1000
1 2500 600
2 2500 600
3 2500 600

2) At what rate would you be indifferent between those two mutually exclusive projects?

A: 20.04%

B: 23.38%

C: 1.35%

D: 1.12%

E: 36.31%

Homework Answers

Answer #1

Cal:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost...
Given the following cash flows for a two mutually exclusive projects (A&B) and assuming 16% cost of capital; year Project A Project B 0 -5000 -1000 1 2500 600 2 2500 600 3 2500 600 2) At what rate would you be indifferent between those two mutually exclusive projects? 20.04% 23.38% 1.35% 1.12% 36.31%
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows...
Tara is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: Cash Flows Year Project Q Project R 0 $(4,000) $(4,000) 1 0 3,500 2 5,000 2,100 IRR 11.8% 28.40% If the firm's required rate of return (r) is 10 percent, which project should be purchased? a. Both projects should be purchased, because the IRRs for both projects exceed the firm's required rate of return. b. Neither project should be accepted, because their NPVs are too small...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: Project...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows...
Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -5000 -5000 1 1000 4500 2 1500 1500 3 2000 1000 4 4000 500 The projects are equally risky, and their cost of capital is 13%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers to two decimal...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: A....
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $10000. Its projected net cash flows are $800, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $14000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. The firm’s cost of capital is 6.00%. Choose the...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$20 $5 $9 $12 Project B -$13 $8 $7 $3 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ 5 million Project B $ 8 million What are the projects' NPVs assuming the...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of return is 16%. Use this information for the next 3 questions. Year Project A Cash Flow Project B Cash Flow 0 ($50,000) ($20,000) 1 15,000 6,000 2 15,000 6,000 3 15,000 6,000 4 13,500 5,400 5 13,500 5,400 6 6,750 5,400 Which of the following statements is true concerning projects A and B? a) Due to time disparity, IRR indicates that project A should...
Project S has a cost of $9,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $9,000 and is expected to produce benefits (cash flows) of $2,700 per year for 5 years. Project L costs $26,000 and is expected to produce cash flows of $7,100 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 10%. Round your answers to the nearest cent. Project S $ ________     Project L $ ________     Which project would be selected, assuming they are mutually exclusive? _________________...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT