Question

Considering IRR and MIRR, which of the following statements is/are correct? MIRR considers all the cash...

Considering IRR and MIRR, which of the following statements is/are correct?

  1. MIRR considers all the cash flows and time value of money.

  2. If Project A’s IRR exceeds Project B’ IRR, then A must have the higher NPV.

  3. Positive MIRR always leads to positive NPV.

  4. Conventional (also known as Normal) cash flows will result in multiple IRRs.

  5. All of the above, except d, are correct statements. (I know this answer is wrong, I got marked off).

Homework Answers

Answer #1

Only statement a. i.e., MIRR considers all the cash flows and time value of money is correct, rest all is a false statements.

MIRR accounts for both positive and negative cash flows.

It is not necessary that a project with higher IRR will have higher NPV. When the conflict arise between IRR and NPV, NPV is preferred. Higher or lower NPV depends on the rate of return or the discounting rate used by the company. IRR assumes NPV to be zero. In such a situation, we can't say for sure that the project with higher IRR wil have higher NPV.

Both MIRR and IRR assumes NPV to be zero. In such a situation, there is no point of positive NPV, be it positive MIRR.

Situation of multiple IRR arises when there is non conventional (non-normal) cash flows are there.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. Which of the following statements is correct? a. A project with conventional cash flows is...
1. Which of the following statements is correct? a. A project with conventional cash flows is one with an initial cash outflow followed by one or more cash inflows. b. The NPV method determines how much the future value of cash inflows exceeds the present value of costs. c. All the answers are correct. d. When two projects are independent, accepting one project implicitly eliminates the other. e. Conventional cash flow patterns could lead to conflicting decisions by NPV and...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC. b. If a project has normal cash flows and its IRR exceeds its WACC, then the project’s NPV must be positive. c. If Project A has a higher IRR than Project B, then Project A must also have a...
Which of the following statements is/are correct? Since depreciation is not a cash expense, it has...
Which of the following statements is/are correct? Since depreciation is not a cash expense, it has no effect on FCF thus no effect on capital budgeting. (this is not the answer, I got marked off). Externality can be either negative or positive factor when estimating FCF. If sunk costs are considered and reflected in a project’s cash flows, then the project’s NPV will be higher thus sunk cost should be included. The inclusion of an externality can never be lead...
Which of the following statements are correct? a. Consider a project that generates a negative cash...
Which of the following statements are correct? a. Consider a project that generates a negative cash flow in year 0 and a positive cash flow in year 1. The NPV rule will always lead to the same decision for this project as the IRR rule. b. Higher NPV projects have longer payback periods. c. Two projects with identical expected cash flows but different risk profiles have the same IRR. d. IRR is affected by the scale of the investment opportunity.
1. Which of the following statements is CORRECT? A. One problem of the IRR method is...
1. Which of the following statements is CORRECT? A. One problem of the IRR method is that it does not consider all cash flows of a project. B. One problem of the IRR method is that it does not take into account the time value of money. C. One problem of the IRR method is that it does not consider the reinvestment of cash inflows. D. One problem of the IRR method is that a dollar received today is valued...
Which of the following statements about internal rate of return (IRR) is false? explain why IRR...
Which of the following statements about internal rate of return (IRR) is false? explain why IRR is the discount rate at which the present value of future expected cash flows is exactly equal to the initial investment. The IRR rule always leads to the same decision as the NPV rule. IRR is the discount rate at which a project's NPV equals zero.
You are considering a project with conventional cash flows and the following characteristics: Discounted Payback 2.95...
You are considering a project with conventional cash flows and the following characteristics: Discounted Payback 2.95 Years NPV $510,000 IRR 12% Which of the following statements is correct given this information? I. The discount rate used in computing the net present value was greater than 12%. II. The payback period must be greater than 2.95 years. III. This project should be accepted as the NPV is positive.
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation : Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $3,225,000....
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,500,000....
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $3,225,000....