Question

Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC. b. If a project has normal cash flows and its IRR exceeds its WACC, then the project’s NPV must be positive. c. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV. d. The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business. e. If Project A has a higher IRR than Project B, then Project A must have the lower NPV.

Homework Answers

Answer #1

a.Internal rate of return (IRR) is the interest rate at which the net present value of all the cash flows (both positive and negative) from a project or investment equal zero. Internal rate of return is used to evaluate the attractiveness of a project or investment. so this statement is not correct

b. yes this statement is correct. IRR exceeds its WACC then the project shall be accepted as it earns higher than its expectation.

c. false this statement is not correct. NPV of the project depends on its size also appart from IRR. So there are posibilities that the project with big size may have lower IRR but have higher NPV.

d. false IRR calculation assumes cash flows are reinvested at the IRR

e. false

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. A: The NPV of a relatively low-risk project should be found using a relatively high WACC B: The lower the WACC used to calculate it, the lower the calculated NPV will be If a project’s NPV is greater than zero, then its IRR must be less than zero C: If a project’s NPV is...
Which of the following statements is correct? Assume the project being considered has normal cash flows,...
Which of the following statements is correct? Assume the project being considered has normal cash flows, with one outflow, followed by a series of inflows: If a project’s NPV is > 0, the IRR must be less than WACC The higher the WACC used to calculate NPV, the lower the calculated NPV will be The NPV’s of relatively risky projects should be found using relatively low WACC’s If a project’s NPV is > 0, the IRR must be less than...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The NPVs of relatively risky projects should be found using relatively low costs of capital. b. If a project's NPV is greater than zero, then its IRR must be less than the cost of capital. c. The higher the cost of capital used to calculate the NPV, the lower the calculated NPV will...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. If a project's NPV is less than zero, then its IRR must be less than the cost of capital. If a project's NPV is greater than zero, then its IRR must...
If a project being considered has normal cash flows, with one outflow followed by a series...
If a project being considered has normal cash flows, with one outflow followed by a series of inflows, which of the following statements is CORRECT? A If a project's NPV is greater than zero, then its IRR must be less than the WACC. B If a project's NPV is greater than zero, then its IRR must be less than zero. C The higher the WACC used to calculate the NPV, the lower the calculated NPV will be. D A project's...
If you assume that a project being considered has normal cash flows, with one outflow followed...
If you assume that a project being considered has normal cash flows, with one outflow followed by a series of inflows, which statement would be correct? Question 11 options: a) The lower the cost of capital used to calculate a project's NPV, the lower the calculated NPV will be. b) If a project's NPV is less than zero, then its IRR must be less than the cost of capital. c) A project’s NPV is found by compounding the cash inflows...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
1. Which of the following statements is correct? a. A project with conventional cash flows is...
1. Which of the following statements is correct? a. A project with conventional cash flows is one with an initial cash outflow followed by one or more cash inflows. b. The NPV method determines how much the future value of cash inflows exceeds the present value of costs. c. All the answers are correct. d. When two projects are independent, accepting one project implicitly eliminates the other. e. Conventional cash flow patterns could lead to conflicting decisions by NPV and...
Which of the following statements is NOT CORRECT? a. The IRR method takes into account the...
Which of the following statements is NOT CORRECT? a. The IRR method takes into account the time value of money b. The IRR method values a dollar received today greater than a dollar that will be received until sometime in the future c. The IRR method takes into account the cash flows over a project’s full life d. The IRR method assumes that the cash flows to be received from a project are to be reinvested at the WACC
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate equal to the project’s IRR. However, in reality, the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, using the modified IRR approach, you can make a more reasonable estimate of a project’s rate of return than the project’s IRR can. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT