Question

1. Which of the following statements is CORRECT? A. One problem of the IRR method is...

1. Which of the following statements is CORRECT?

A. One problem of the IRR method is that it does not consider all cash flows of a project.

B. One problem of the IRR method is that it does not take into account the time value of money.

C. One problem of the IRR method is that it does not consider the reinvestment of cash inflows.

D. One problem of the IRR method is that a dollar received today is valued the same as a dollar to be received in the future.

E. One problem of the IRR method is that it assumes that the cash inflows are reinvested at the IRR, which assumption may not be reasonable.

2. A company has bonds outstanding that mature in 8 years, have a par value of $1,000, and have a coupon interest payment of $80 paid annually. The market interest rate is 7.1% per annum for these bonds. What is the bond's estimated price in the market?

A. $1,025.71

B. $983.78

C. $1,117.92

D. $1,053.53

E. $1,184.96

3. Which of the following statements is CORRECT?

A. The longer a project’s payback period, the better the project.

B. One problem with the payback method for evaluating projects is that it does not consider the time value of money.

C. If a project’s payback is positive, then the project should be rejected because it will also have a negative NPV.

D. The payback method considers the cash flows of a project beyond the payback period.

E. The authors of the textbook recommend the payback method as the best approach to evaluate capital investment proposals.

Homework Answers

Answer #1

1. Correct option is E.

One problem of the IRR method is that it assumes that the cash inflows are reinvested at the IRR, which assumption may not be reasonable.

Other options are incorrect as the IRR method do considers all the cash flows and also considers the time value of money. It also considers that the cash inflows are reinvested.

--> It is one of the limitation of IRR as a method of capital budgeting technique that it considers that all the cash inflows of the project are reinvested at IRR only which is wrong.

Hence correct option is E.

Hope it clarifies!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statements is CORRECT? A) One defect of the IRR method is that...
Which of the following statements is CORRECT? A) One defect of the IRR method is that it does not take account of cash flows over a project’s full life. B) One defect of the IRR method is that it does not take account of the time value of money. C) One defect of the IRR method is that it does not take account of the cost of capital. D) One defect of the IRR method is that it values a...
Which of the following statements is NOT CORRECT? a. The IRR method takes into account the...
Which of the following statements is NOT CORRECT? a. The IRR method takes into account the time value of money b. The IRR method values a dollar received today greater than a dollar that will be received until sometime in the future c. The IRR method takes into account the cash flows over a project’s full life d. The IRR method assumes that the cash flows to be received from a project are to be reinvested at the WACC
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC. b. If a project has normal cash flows and its IRR exceeds its WACC, then the project’s NPV must be positive. c. If Project A has a higher IRR than Project B, then Project A must also have a...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate equal to the project’s IRR. However, in reality, the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, using the modified IRR approach, you can make a more reasonable estimate of a project’s rate of return than the project’s IRR can. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $450,000. The project’s expected cash flows are: Year Cash...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $400,000. The project’s expected cash flows are: Year...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Fuzzy Button Clothing Company is analyzing a project that requires an initial investment of $500,000. The project’s...
1. Multiple internal rates or return occur when: Select one: A. The project’s cash flows are...
1. Multiple internal rates or return occur when: Select one: A. The project’s cash flows are larger earlier in the life of the project. B. The project’s cash flows are larger later in the life of the project. C. When the project’s cash flows experience normal cash flow streams (i.e. one sign change). D. When the project’s cash flows experience non-normal cash flow streams (i.e. two or more sign changes). E. When the IRR is equal to the WACC. 2....
Four of the following statements are truly disadvantages of the regular payback method, but one is...
Four of the following statements are truly disadvantages of the regular payback method, but one is not a disadvantage of this method. Which one is NOT a disadvantage of the payback method? a. Ignores cash flows beyond the payback period. b. Does not directly account for the time value of money. c. Does not provide any indication regarding a project’s liquidity or risk. d. Lacks an objective, market-determined benchmark for making decisions. e. Does not take account of differences in...
1. Which of the following statements is correct? a. A project with conventional cash flows is...
1. Which of the following statements is correct? a. A project with conventional cash flows is one with an initial cash outflow followed by one or more cash inflows. b. The NPV method determines how much the future value of cash inflows exceeds the present value of costs. c. All the answers are correct. d. When two projects are independent, accepting one project implicitly eliminates the other. e. Conventional cash flow patterns could lead to conflicting decisions by NPV and...