Question

Question 1 A new production system for a factory is to be purchased and installed for...

Question 1

A new production system for a factory is to be purchased and installed for $142,299. This system will save approximately 300,000 kWh of electric power each year for a 6-year period. Assume the cost of electricity is $0.10 per kWh, and factory MARR is 15% per year, and the salvage value of the system will be $9,077 at year 6. Using the PW method to analyzes if this investment is economically justified

A- calculate the PW of the above investment and insert the result below.

Homework Answers

Answer #1

Answer

The Present worth has been calculated as follows:

1. Calculate PW of yearly savings

PV Annuity​ = C × [1−(1+i)−n​]​ / i

where, C= Costy of electricity saved every year

i = MARR

n = Number of years

Plugging the same numbers as above into the equation, here is the result:

PV Annuity​ = 300000* 0.10 × [1−(1+.15)−6​]​ / 0.15

= $113,534.5

2. Calculate Present Worth of the Salvage Amount

PV = FV/(1+r)n

PV = Present value, also known as present discounted value, is the value on a given date of a payment.
FV = This is the projected amount of money in the future
r = the periodic rate of return, interest or inflation rate, also known as the discounting rate.
n = number of years

Thus, PV = 9077 / (1.15)6

= $3924.2

Thus, the PW of the above investment = Present Worth of Salvage Value + Present Worth of yearly savings

= 3924.2 + 113,534.5

= $117458.74

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
QUESTION 1 A new production system for a factory is to be purchased and installed for...
QUESTION 1 A new production system for a factory is to be purchased and installed for $132,564. This system will save approximately 300,000 kWh of electric power each year for a 6-year period. Assume the cost of electricity is $0.10 per kWh, and factory MARR is 15% per year, and the salvage value of the system will be $9,792 at year 6. Using the PW method to analyzes if this investment is economically justified A- calculate the PW of the...
A new production system for a factory is to be purchased and installed for $148,907. This...
A new production system for a factory is to be purchased and installed for $148,907. This system will save approximately 300,000 kWh of electric power each year for a 6-year period. Assume the cost of electricity is $0.10 per kWh, and factory MARR is 15% per year, and the salvage value of the system will be $9,033 at year 6. Using the PW method to analyzes if this investment is economically justified A- calculate the PW of the above investment...
A marine engineering firm purchased and installed a new production facility for fabrication of its line...
A marine engineering firm purchased and installed a new production facility for fabrication of its line of fluid machinery at a cost of $750,000, funded by a bank loan at an interest rate of 8.5% for a period of five (5) years. The firm’s cost accountants determined that, because of the efficiency of the new facilities, the company’s production costs would be reduced by $300,000 per year over the five year term of the bank loan. A Present Value Analysis...
An​ old, heavily used warehouse currently has an incandescent lighting system. The lights run essentially 24​...
An​ old, heavily used warehouse currently has an incandescent lighting system. The lights run essentially 24​ hr/day, 365​ days/yr and draw about 8kW of power. Consideration is being given to replacing these lights with fluorescent lights to save on electricity. It is estimated that the same level of lighting can be achieved with 4.3kW of fluorescent lights. Replacement of the lights will cost about ​$7000. Bulb replacement and other maintenance are not expected to be significantly different. Electricity for the...
A local private hospital has just purchased a new computerized patient information system with an installed...
A local private hospital has just purchased a new computerized patient information system with an installed cost of $100,000. For tax purposes, the information system is treated as five-year MACRS property. The system would have a salvage value of about $5,000 at the end of five years. (i) What is the depreciation allowance for the third year of use? (ii) What is the depreciation allowance for the fifth year of use?
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $700,000. This...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $700,000. This cost will be depreciated straight-line to zero over the project’s 6-year life, at the end of which the sausage system can be scrapped for $94,000. The sausage system will save the firm $201,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $53,000. What is the aftertax salvage value of the equipment? (Do not round...
Dog Up! Franks is looking at a new sausage system with an installed cost of $530,400....
Dog Up! Franks is looking at a new sausage system with an installed cost of $530,400. This cost will be depreciated straight-line to zero over the project's 6-year life, at the end of which the sausage system can be scrapped for $81,600. The sausage system will save the firm $163,200 per year in pretax operating costs, and the system requires an initial investment in net working capital of $38,080.    If the tax rate is 22 percent and the discount...
QUESTION 1 The term "Slip" indicates the difference between the motor's synchronous speed and the no-load...
QUESTION 1 The term "Slip" indicates the difference between the motor's synchronous speed and the no-load speed True False 1 points    QUESTION 2 Wet Bulb (WB) Temperature: is for the temperature reading form an ordinary mercury bulb thermometer or regular temperature sensor. True False 1 points    QUESTION 3 The refrigerant (R-134a) is the new replacement of the refrigerant (R-22) as it is less harmful to the environment. True False 1 points    QUESTION 4 Draft Gauge and Bourdon...
Sage is looking at a new system with an installed cost of $400,800. This cost will...
Sage is looking at a new system with an installed cost of $400,800. This cost will be depreciated straight-line to zero over the project's 4-year life, at the end of which the system can be scrapped for $60,200. The system will save the firm $180,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $38,500. All of the net working capital will be recovered at the end of the project. The...
Installing an automated production system costing $300,000 is initially expected to save Zia Corporation $52,000 in...
Installing an automated production system costing $300,000 is initially expected to save Zia Corporation $52,000 in expenses annually. If the system needs $7,500 in operating and maintenance costs each year and has a salvage value of $30,000 at year 10, what is the IRR of this system? If the should this system be purchased? (show solution steps using trial and error, excel bases solutions are not allowed)