Which of the following is the correct order for allocating overhead costs using activity-based costing?
a.determine overhead costs; directly trace and distribute overhead costs to support and production activities; allocate support activity costs to production activities; apply production activity costs to products
b.determine overhead costs; directly trace and distribute overhead costs to support and production activities; apply production activity costs to products; allocate support activity costs to production activities
c.directly trace and distribute overhead costs to support and production activities; determine overhead costs; allocate support activity costs to production activities; apply production activity costs to products
d.allocate support activity costs to production activities; determine overhead costs; directly trace and distribute overhead costs to support and production activities; apply production activity costs to products
The correct order for allocating overhead costs using activity-based costing is: |
determine overhead costs; directly trace and distribute overhead costs to support and production activities; allocate support activity costs to production activities; apply production activity costs to products |
The overhead costs are determined first and traced to support and production activities. |
The support activity costs are then allocated to production activities and production activity costs are applied to products. |
Option A is correct |
Get Answers For Free