Question

ob Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

ob Costs Using Activity-Based Costing

Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows:

Activity Cost Driver Amount of Driver
Materials handling $117,500 Number of moves 5,000
Engineering 128,000 Number of change orders 8,000
Other overhead 265,200 Direct labor hours 52,000

Heitger worked on four jobs in July. Data are as follows:

Job 13-43 Job 13-44 Job 13-45 Job 13-46
Beginning balance $24,400 $17,900 $2,500 $0
Direct materials $6,800 $8,950 $12,000 $9,900
Direct labor cost $970 $1,030 $1,570 $130
Job 13-43 Job 13-44 Job 13-45 Job 13-46
Number of moves 41 46 35 6
Number of change orders 33 43 15 23
Direct labor hours 970 1,030 1,570 130

By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.

Required:

1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.

Materials handling rate $  per move
Engineering rate $  per change order
Other overhead rate $  per direct labor hour

Hide Feedback

Incorrect

Check My Work Feedback

1. In job-order costing, departmental overhead rates and activity-based costing affect only the application of overhead and is put on the job-order costing sheet and must include all drivers for which overhead is applied.

Hide

2. Prepare job-order cost sheets for each job showing all costs through July 31.

Homework Answers

Answer #1

1. Activity Rates for the Overhead Cost Pools:

Cost Pool Activity Rate
Materials Handling $ 23.50 per move
Engineering $ 16 per change order
Other Overhead $ 5.1 per direct labor hour

2. Job order cost sheets:

Job 13-43 13-44 13-45 13-46
Beginning balance $ 24,400 $ 17,900 $ 2,500 $ 0
Added during July:
Direct Materials 6,800 8,950 12,000 9,900
Direct Labor 970 1,030 1,570 130
Manufacturing Overhead:
Material Handling 963.50 1,081 822.50 141
Engineering 528 688 240 368
Other Overhead 4,947 5,253 8,007 663
Total Costs added during July 14,208.50 17,002 22,639.50 11,202
Total Manufacturing Costs 38,608.50 34,902 25,139.50 11,202
Cost of Goods Manufactured and Transferred Out (38,608.50) (34,902) 0 0
Ending Work in Process 0 0 25,139.50 11,202
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost    Driver Amount of Driver Materials handling $ 72,000      Number of moves 3,000   Engineering 165,000      Number of change orders 10,000   Other overhead 280,000      Direct labor hours 50,000   Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows: Zayner Company is a job order costing company that uses activity-based costing (ABC) to apply manufacturing overhead to different jobs. Zayner identified three activities and the related cost drivers. The budgeted information (budget) for the year is as follows: Activity Cost Driver Amount of Driver Engineering...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $135,000 for the year and the estimated direct labor hours were 15,000 hours. In May, Job #378 was completed. Direct materials totaled $8,500. Total labor costs were $14,000 at $16 per hour. At the end of the year, it was determined that the company worked 16,000 direct labor...
Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $710. During July,...
Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $710. During July, prime costs added to the job totaled $600. Of that amount, direct materials were three times as much as direct labor. The ending balance of the job was $1,600. Required: 1. What was overhead applied to the job during July? $ 2. What was direct materials for Job 46 for July? Direct labor? If rounding is required, round your answers to the nearest cent....
Carlon, Inc. uses a job-order costing system and applies overhead based on direct labor dollars. Job...
Carlon, Inc. uses a job-order costing system and applies overhead based on direct labor dollars. Job 316 was started in July and incurred the following costs in July: Direct materials $950 Direct labor $1,050 Applied overhead $1,260 The job was completed in August with an additional $2,100 in direct material cost and $1,400 in additional direct labor cost. What was the total cost of Job 316 at the end of August?
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide rate of 90% of direct materials cost. Br3-Pf Company began work on four jobs during June. Information related to the four jobs appears below: Job #1 Job #2 COSTS ADDED DURING JUNE direct materials .............. $5,800 $7,500 direct labor .................. $7,300 $6,300 Job #3 Job #4 COSTS ADDED DURING JUNE direct materials .............. $8,200 $6,400 direct labor .................. $7,920 $7,560 By the end of...
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at...
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at $25 per machine hour. The company is considering adopting an activity-based costing system with the following data: Activity Cost Driver Rate Materials handling Pounds of material $1.50 Lathe work Number of parts $1.00 Milling Number of machine hours $8.00 Grinding Number of turns $0.40 Testing Number of units tested $15.00 The two jobs processed in the month of May had the following characteristics: Job...
Snappy Company uses job-order costing and applies overhead costs to jobs using a pre-determined overhead rate...
Snappy Company uses job-order costing and applies overhead costs to jobs using a pre-determined overhead rate of $12 per direct labor hour. During 2020, Snappy Company worked on the following jobs Job #16 Job #28 Job #35 beginning cost ............. $3,500 $1,600 $2,000 direct materials used ...... $2,800 $3,700 $2,600 direct labor cost .......... $2,000 $5,300 $3,600 direct labor hours ......... 200 hours 300 hours 280 hours By the end of 2020, Job #16 and Job #28 had been completed....
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at...
Oxnard Company uses a volume-based costing system that applies overhead cost based on machine hours at $25 per machine hour. The company is considering adopting an activity-based costing system with the following data: Activity Cost Driver Rate Materials handling Pounds of material $1.50 Lathe work Number of parts $1.00 Milling Number of machine hours $8.00 Grinding Number of turns $0.40 Testing Number of units tested $15.00 The two jobs processed in the month of May had the following characteristics: Job...