Question

Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

Job Costs Using Activity-Based Costing

Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows:

Activity Cost    Driver Amount of Driver
Materials handling $ 72,000      Number of moves 3,000  
Engineering 165,000      Number of change orders 10,000  
Other overhead 280,000      Direct labor hours 50,000  

Heitger worked on four jobs in July. Data are as follows:

Job 13-43 Job 13-44 Job 13-45 Job 13-46
Beginning balance $20,300 $19,800 $2,300 $0
Direct materials $6,500 $8,900 $12,700 $9,800
Direct labor cost $18,000 $20,000 $32,000 $2,400
Job 13-43 Job 13-44 Job 13-45 Job 13-46
Number of moves 44 52 29 5
Number of change orders 30 40 20 20
Direct labor hours 900 1,000 1,600 120

By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.

Required:

1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.

Materials handling rate $ per move
Engineering rate $ per change order
Other overhead rate $ per direct labor hour

Feedback

1. In job-order costing, departmental overhead rates and activity-based costing affect only the application of overhead and is put on the job-order costing sheet and must include all drivers for which overhead is applied.

2. Prepare job-order cost sheets for each job showing all costs through July 31.

If an amount is zero, enter "0".

Heitger Company
Job-Order Cost Sheets
Job 13-43 Job 13-44 Job 13-45 Job 13-46
Balance, July 1 $ $ $ $
Direct materials
Direct labor cost
Materials handling
Engineering
Other overhead
Total $ $ $ $

Feedback

2. The job-order cost sheet must include a unique number or name for this particular job, all direct costs, and all overhead costs associated with the job.

3. Calculate the balance in Work in Process on July 31.
$

4. Calculate the cost of goods sold for July.
$

5. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46?

$   lower

How would the cost of the other jobs be affected?
no effect

Homework Answers

Answer #1
1) Activity rates
Materials handling rate 24 per move
engineering rate 16.5 per change order
other overhead rate 5.6 per direct labor hour
2) Job order cost sheet
job 13-43 job 13-44 job13-45 job 13-46
Balance,july 1 20,300 19,800 2,300 0
direct materials 6,500 8,900 12,700 9,800
direct labor cost 18000 20000 32000 2400
materials handling 1056 1248 696 120
engineering 495 660 330 330
other overhead 5040 5600 8960 672
total 51,391 56,208 56,986 13,322
3) Balance of work in process july 31 70,308
(job 45 and job 46)
4) cost of goods sold for july 107,599
(job 43 and 44)
5) difference in cost will be 330 lower
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ob Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
ob Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $117,500 Number of moves 5,000 Engineering 128,000 Number of change orders 8,000 Other overhead 265,200 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows: Zayner Company is a job order costing company that uses activity-based costing (ABC) to apply manufacturing overhead to different jobs. Zayner identified three activities and the related cost drivers. The budgeted information (budget) for the year is as follows: Activity Cost Driver Amount of Driver Engineering...
Activity Cost Pools, Activity Rates, and Product Costs using Activity-Based Costing Caldwell Home Appliances Inc. is...
Activity Cost Pools, Activity Rates, and Product Costs using Activity-Based Costing Caldwell Home Appliances Inc. is estimating the activity cost associated with producing ovens and refrigerators. The indirect labor can be traced into four separate activity pools, based on time records provided by the employees. The budgeted activity cost and activity-base information are provided as follows: Activity Activity Pool Cost Activity Base Procurement $144,480 Number of purchase orders Scheduling 6,300 Number of production orders Materials handling 30,420 Number of moves...
Carlon, Inc. uses a job-order costing system and applies overhead based on direct labor dollars. Job...
Carlon, Inc. uses a job-order costing system and applies overhead based on direct labor dollars. Job 316 was started in July and incurred the following costs in July: Direct materials $950 Direct labor $1,050 Applied overhead $1,260 The job was completed in August with an additional $2,100 in direct material cost and $1,400 in additional direct labor cost. What was the total cost of Job 316 at the end of August?
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $710. During July,...
Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $710. During July, prime costs added to the job totaled $600. Of that amount, direct materials were three times as much as direct labor. The ending balance of the job was $1,600. Required: 1. What was overhead applied to the job during July? $ 2. What was direct materials for Job 46 for July? Direct labor? If rounding is required, round your answers to the nearest cent....
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide rate of 90% of direct materials cost. Br3-Pf Company began work on four jobs during June. Information related to the four jobs appears below: Job #1 Job #2 COSTS ADDED DURING JUNE direct materials .............. $5,800 $7,500 direct labor .................. $7,300 $6,300 Job #3 Job #4 COSTS ADDED DURING JUNE direct materials .............. $8,200 $6,400 direct labor .................. $7,920 $7,560 By the end of...
Doede Corporation uses activity-based costing to compute product margins. In the first stage, the activity-based costing...
Doede Corporation uses activity-based costing to compute product margins. In the first stage, the activity-based costing system allocates two overhead accounts--equipment depreciation and supervisory expense--to three activity cost pools--Machining, Order Filling, and Other--based on resource consumption. Data to perform these allocations appear below: Overhead costs: Equipment depreciation $ 92,000 Supervisory expense $ 4,000 Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Machining Order Filling Other Equipment depreciation 0.60 0.20 0.20 Supervisory expense 0.30 0.20 0.50 In the...
Doede Corporation uses activity-based costing to compute product margins. In the first stage, the activity-based costing...
Doede Corporation uses activity-based costing to compute product margins. In the first stage, the activity-based costing system allocates two overhead accounts--equipment depreciation and supervisory expense--to three activity cost pools--Machining, Order Filling, and Other--based on resource consumption. Data to perform these allocations appear below: Overhead costs: Equipment depreciation $ 107,000 Supervisory expense $ 9,900 Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Machining Order Filling Other Equipment depreciation 0.60 0.30 0.10 Supervisory expense 0.60 0.20 0.20 In the...