Question

A company began work in 2020 on a contract for $7,700. Other data are as follows:...

A company began work in 2020 on a contract for $7,700. Other data are as follows:

2020 2021
Costs incurred to date $3,000 $5,600
Estimated Costs to complete 2,000 ----------
Billings to date 3,700 7,700
Collections to date 1,000 4,800

On the company’s balance sheet at December 31, 2020, under the percentage-of-completion method, an inventory (or current liability) of $_____________ will be reported related to this project.

Homework Answers

Answer #1

Solution:

Cost incurred till date $ 3,000
Total Estimated cost $ 5,000 =3000+2000
% Completion 60% =3000/5000
Contract price $ 7,700
Revenue to be recognized for 2020 $ 4,620 =7700*60%
Billings to date $ 3,700

On the company’s balance sheet at December 31, 2020, under the percentage-of-completion method,

an inventory of $ 920 ( 4,620 - 3,700 ) will be reported related to this project.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company began work in 2020 on a contract for $6,800. Other data are as follows:...
A company began work in 2020 on a contract for $6,800. Other data are as follows:                                                        2020                         2021 2020 2021 costs incurred to date $3,100 $5,600 Estimated Costs to complete 2,000 ----------- Billings to date 3,400 6,800 Collections to date 2,000 4,800 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is                          .
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows:                                                        2020                         2021 Costs incurred to date                 $3,000 $5,600 Estimated costs to complete         2,000       — Billings to date    3,100                   7,800 Collections to date                       1,000                      4,400 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following data pertain to the first two years that the contract was in process. 2020                              2021               Costs incurred to date                                    $   570,000                  $1,557,500    Estimated costs to complete as of 12/31       1,330,000                         667,500 Billings to date                                                     650,000                     1,250,000    Cash collections to date                                     600,000                     1,150,000 1. Using the percentage-of-completion method: A. Compute gross profit to be reported in each...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $40,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          18,000         28,000 Collections to date                     5,000           15,000         26,000 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is___________________________ .
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows: 2018     2019 Costs incurred to date €9,000,000 €14,000,000 Estimated costs to complete 6,000,000 — Billings to date 7,000,000 21,000,000 Collections to date 5,000,000 18,000,000 8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is A. €3,600,000. B. €4,000,000. C. €5,400,000. D. €6,000,000. 9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow: 2020 2021 Costs incurred during the year $615,810 $1,422,000 Estimated costs to complete, as of December 31 963,190 –0– Billings during the year 426,000 2,170,000 Collections during the year 343,000 1,520,000 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. What...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of $5,820,000. Bramble estimated total construction costs would be $4,016,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date. $1,506,000 $2,652,000 $4,610,000 Estimated costs to complete. 2,510,000 1,768,000 -0- Customer billings to date 2,220,000 4,016,000 5,620,000 Collections to date 2,020,000 3,520,000 5,520,000 Fill in the...