Question

A company began work in 2020 on a contract for $7,800. Other data are as follows:...

A company began work in 2020 on a contract for $7,800. Other data are as follows:

   

                                                   2020                         2021

Costs incurred to date                 $3,000 $5,600

Estimated costs to complete         2,000       —

Billings to date    3,100                   7,800

Collections to date                       1,000                      4,400

If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company began work in 2020 on a contract for $6,800. Other data are as follows:...
A company began work in 2020 on a contract for $6,800. Other data are as follows:                                                        2020                         2021 2020 2021 costs incurred to date $3,100 $5,600 Estimated Costs to complete 2,000 ----------- Billings to date 3,400 6,800 Collections to date 2,000 4,800 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is                          .
A company began work in 2020 on a contract for $7,700. Other data are as follows:...
A company began work in 2020 on a contract for $7,700. Other data are as follows: 2020 2021 Costs incurred to date $3,000 $5,600 Estimated Costs to complete 2,000 ---------- Billings to date 3,700 7,700 Collections to date 1,000 4,800 On the company’s balance sheet at December 31, 2020, under the percentage-of-completion method, an inventory (or current liability) of $_____________ will be reported related to this project.
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...
Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows: 2018     2019 Costs incurred to date €9,000,000 €14,000,000 Estimated costs to complete 6,000,000 — Billings to date 7,000,000 21,000,000 Collections to date 5,000,000 18,000,000 8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is A. €3,600,000. B. €4,000,000. C. €5,400,000. D. €6,000,000. 9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow: 2020 2021 Costs incurred during the year $615,810 $1,422,000 Estimated costs to complete, as of December 31 963,190 –0– Billings during the year 426,000 2,170,000 Collections during the year 343,000 1,520,000 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. What...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $40,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          18,000         28,000 Collections to date                     5,000           15,000         26,000 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is___________________________ .
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of $5,820,000. Bramble estimated total construction costs would be $4,016,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date. $1,506,000 $2,652,000 $4,610,000 Estimated costs to complete. 2,510,000 1,768,000 -0- Customer billings to date 2,220,000 4,016,000 5,620,000 Collections to date 2,020,000 3,520,000 5,520,000 Fill in the...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a...
Ivanhoe Construction Company uses the percentage-of-completion method of accounting. In 2021, Ivanhoe began work on a contract it had received which provided for a contract price of $39500000. Other details follow: 2021 Costs incurred during the year $18800000 Estimated costs to complete as of December 31 12800000 Billings during the year 17500000 Collections during the year 9700000 What should be the gross profit recognized in 2021? $7900000 $4700000 $20700000 $1566667
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Correct answer iconYour answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT