Question

Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:...

Kiner, Inc. began work in 2018 on a contract for €21,000,000. Other data are as follows:

2018     2019

Costs incurred to date €9,000,000 €14,000,000

Estimated costs to complete 6,000,000 —

Billings to date 7,000,000 21,000,000

Collections to date 5,000,000 18,000,000

8. If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2018 is

A. €3,600,000.

B. €4,000,000.

C. €5,400,000.

D. €6,000,000.

9. If Kiner uses the cost-recovery method, the gross profit to be recognized in 2019 is

A. €3,400,000.

B. €7,000,000.

C. €3,500,000.

D. €14,000,000.

10. Remington Construction Company uses the percentage-of-completion method. During 2018, the company entered into a fixed-price contract to construct a building for Sherman Company for £36,000,000. The following details pertain to the contract:

At December 31, 2018 At December 31, 2019

Percentage of completion 25% 60%

Estimated total cost of contract £27,000,000 £30,000,000

Gross profit recognized to date 2,250,000     3,600,000

The amount of construction costs incurred during 2019 was

A. £18,000,000.

B. £11,250,000.

C. £6,750,000.

D. £3,000,000.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company began work in 2020 on a contract for $6,800. Other data are as follows:...
A company began work in 2020 on a contract for $6,800. Other data are as follows:                                                        2020                         2021 2020 2021 costs incurred to date $3,100 $5,600 Estimated Costs to complete 2,000 ----------- Billings to date 3,400 6,800 Collections to date 2,000 4,800 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is                          .
A company began work in 2020 on a contract for $7,800. Other data are as follows:...
A company began work in 2020 on a contract for $7,800. Other data are as follows:                                                        2020                         2021 Costs incurred to date                 $3,000 $5,600 Estimated costs to complete         2,000       — Billings to date    3,100                   7,800 Collections to date                       1,000                      4,400 If the company uses the percentage-of-completion method, for the journal entry that records construction revenue, construction expense, and gross profit for 2020, how much will be recorded for Construction in Process?
Percentage-of-completion method. Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction began in 2018 and...
Percentage-of-completion method. Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction began in 2018 and is expected to be completed in 2020. Data for 2018 and 2019 are: Costs incurred to date Estimated costs to complete Arshdeep uses the percentage-of-completion method. Instructions 2018 $4,500,000 18,000,000 2019 $13,000,000 12,000,000 (a) How much gross profit should be reported for 2018? Show your computation. (b) How much gross profit should be reported for 2019? (c) Make the journal entry to record the...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work...
Windham Construction Company uses the percentage of completion method of accounting. In 2018 Windham started work on a two-year contract with a total price of $15,000,000. Data for 2018 and 2019 are presented below: (Follow GAAP)                                                                  2018                            2019                       Costs incurred to date             $7,200,000                  $12,050,000             Estimated costs to complete   4,800,000                         - 0 -             Billings during the year          6,000,000                      9,000,000             Collections during the year     4,200,000                      8,900,000 (a)       How much...
Gomez, Inc. began work in 2010 on contract #3814, which provided for a contract price of...
Gomez, Inc. began work in 2010 on contract #3814, which provided for a contract price of $7,200,000. Other details follow: 2010 2011 Costs incurred during the year $1,200,000 $3,675,000 Estimated costs to complete, as of December 31 3,600,000 0 Billings during the year 1,350,000 5,400,000 Collections during the year 900,000 5,850,000 14. Assume that Gomez uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2010 is a. $450,000. b. $600,000....
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract...
In 2016 the ole construction corp began construction work under a 3 year contract. The contract price was $1,600,000. The Job was completed in 2018.                                                                                 2016                       2017                       2018 Costs incurred to date                                    400000                  935000                  1070000 Estimated costs to complete                       700000                  165000                  0 Billings to date                                                  300000                  900000                  1600000 Collections to date                                           270000                  810000                  1525000 Compute the amount of Gross Profit to be recognized for 2016 and 2017 assuming that ole is required to recognize revenue overtime. Compute the...
During 2018, Miners Inc. started a construction job with a contract price of $20,000. The job...
During 2018, Miners Inc. started a construction job with a contract price of $20,000. The job was completed in 2020 and information for the three years of construction is as follows: Required: Using the PERCENTAGE-OF-COMPLETION (cost-to-cost) method: Show and label all calculations. (a)   Calculate the total percentage complete for the contract at the end of each year. Round the percentage complete to two decimal places (ie. 12.34%). (b) Calculate the amount of gross profit that Miners should be recognized each...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT