Question

Davies Company's Utility Cost at various levels of activity are shown below: Month Units Utility Cost...

Davies Company's Utility Cost at various levels of activity are shown below: Month Units Utility Cost April 5,000 $7,400 May 7,300 $9,100 June 8,000 $9,800 July 6,500 $8,200 Requirement 1: Given the above information, use the High-Low method to compute the variable and fixed portion of utility cost. Show your computations and indicate the cost equation. (5 points) Requirement 2: Using the equation from requirement 2, compute total cost estimate if 6,000 units are produced. Show your computations. (5 points)

Homework Answers

Answer #1

Solution:

From the given data we need to find total cost of 6,000 units: Calculations are follows,

Variable cost :

=(Total cost at highest level - Total cost at lowest level) / (Highest level-Lowest level)

=($9,800- $7,400) / (8,000 - 5,000)

= $2,400 / 3,000

= $0.8 per unit

Variable cost :

= (8,000*$0.8)

Variable cost = $6,400

Fixed cost : (Total cost - variable cost)

= $9,800 - ($0.8 * 8,000)

= $9,800 - $6,400

= $3,400

Cost equation: y=$3,400 + 0.8x

where,

y = Total cost

x = number of units

Hence total cost for 6,000  units :

= $3,400 + ($0.8 * 6,000)

= $3,400 + $4,800

= $8,200

Total cost for 6,000  units $8,200


Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Davies Company's Utility Cost at various levels of activity are shown below: Month           Units        Utility Cost...
Davies Company's Utility Cost at various levels of activity are shown below: Month           Units        Utility Cost April              70,000      $198,000 May               60,000      $174,000 June               80,000      $222,000 July                 90,000      $246,000 Requirement 1: Given the above information, use the High-Low method to compute the variable and fixed portion of utility cost. Show your computations and indicate the cost equation. (5 points) Requirement 2: Using the equation from requirement 2, compute total cost estimate if 75,000 units are produced. Show your computations.
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 198,260 May 42,000 $ 172,460 June 62,000 $ 224,060 July 72,000 $ 249,860 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 58,800 Supervisory salaries (fixed) 49,000 Maintenance (mixed) 64,660 Total overhead cost $ 172,460 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 217,820 May 38,000 $ 190,420 June 58,000 $ 245,220 July 68,000 $ 272,620 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 70,000 Maintenance (mixed) 63,420 Total overhead cost $ 190,420 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 199,940 May 38,000 $ 172,640 June 58,000 $ 227,240 July 68,000 $ 254,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 54,000 Maintenance (mixed) 61,640 Total overhead cost $ 172,640 Nova Company’s...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $173,870        May 39,000    $151,570        June 59,000    $196,170        July 69,000    $218,470   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 42,900     Supervisory salaries (fixed) 46,000   Maintenance (mixed) 62,670   Total overhead cost $ 151,570 The...
Abacus Company sells its product for $180 per unit. Its actual and projected sales follow.   ...
Abacus Company sells its product for $180 per unit. Its actual and projected sales follow.    Units Dollars   April (actual) 6,000       $1,080,000      May (actual) 2,000       360,000      June (budgeted) 7,000       1,260,000      July (budgeted) 6,500       1,170,000      August (budgeted) 3,800       684,000    All sales are on credit. Recent experience shows that 22% of credit sales is collected in the month of the sale, 48% in the month after the sale, 28% in the second...
Abacus Company sells its product for $180 per unit. Its actual and projected sales follow.   ...
Abacus Company sells its product for $180 per unit. Its actual and projected sales follow.    Units Dollars   April (actual) 6,000       $1,080,000      May (actual) 2,000       360,000      June (budgeted) 7,000       1,260,000      July (budgeted) 6,500       1,170,000      August (budgeted) 3,800       684,000    All sales are on credit. Recent experience shows that 22% of credit sales is collected in the month of the sale, 48% in the month after the sale, 28% in the second...
Abacus Company sells its product for $180 per unit. Its actual and projected sales follow.   ...
Abacus Company sells its product for $180 per unit. Its actual and projected sales follow.    Units Dollars   April (actual) 6,000       $1,080,000      May (actual) 2,000       360,000      June (budgeted) 7,000       1,260,000      July (budgeted) 6,500       1,170,000      August (budgeted) 3,800       684,000    All sales are on credit. Recent experience shows that 22% of credit sales is collected in the month of the sale, 48% in the month after the sale, 28% in the second...
Abacus Company sells its product for $210 per unit. Its actual and projected sales follow.   ...
Abacus Company sells its product for $210 per unit. Its actual and projected sales follow.    Units Dollars   April (actual) 6,500       $1,365,000      May (actual) 2,400       504,000      June (budgeted) 7,500       1,575,000      July (budgeted) 4,500       945,000      August (budgeted) 4,100       861,000    All sales are on credit. Recent experience shows that 26% of credit sales is collected in the month of the sale, 44% in the month after the sale, 26% in the second...
Abacus Company sells its product for $210 per unit. Its actual and projected sales follow.   ...
Abacus Company sells its product for $210 per unit. Its actual and projected sales follow.    Units Dollars   April (actual) 6,500       $1,365,000      May (actual) 2,400       504,000      June (budgeted) 7,500       1,575,000      July (budgeted) 4,500       945,000      August (budgeted) 4,100       861,000    All sales are on credit. Recent experience shows that 26% of credit sales is collected in the month of the sale, 44% in the month after the sale, 26% in the second...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT