Question

Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

Crosshill Company’s total overhead costs at various levels of activity are presented below:

Month Machine-Hours Total Overhead Cost
     April 49,000    $173,870  
     May 39,000    $151,570  
     June 59,000    $196,170  
     July 69,000    $218,470  

Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:

  Utilities (variable) $ 42,900  
  Supervisory salaries (fixed) 46,000
  Maintenance (mixed) 62,670
  Total overhead cost $ 151,570

The company wants to break down the maintenance cost into its variable and fixed cost elements.

Required:

1. Estimate how much of the $218,470 of overhead cost in July was maintenance cost. (Hint: To do this, first determine how much of the $218,470 consisted of utilities and supervisory salaries. Think about the behaviour of variable and fixed costs within the relevant range.) (Do not round intermediate calculations.)

Maintenance cost of July

2. Using the high–low method, estimate a cost formula for maintenance. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)

Machine- Hours Maintenance Cost
High activity level
Low activity level
Change
Variable cost element per MH
Fixed cost element
Y = + X

3. Express the company’s total overhead cost in the form Y = a + bX. (Do not round your intermediate calculations. Round the "Variable cost per unit" to 2 decimal places.)

Variable Cost per
Machine-Hour Fixed Cost
Utilities cost
Supervisory salaries cost
Maintenance cost
Total overhead cost

4. What total overhead cost would you expect to be incurred at an activity level of 44,000 machine-hours? (Do not round intermediate calculations.)

Total overhead cost

Homework Answers

Answer #1
1
Total overhead cost 218470
Less: Utilities 75900 =42900/39000*69000
Less: Supervisory salaries 46000
Maintenance cost in July 96570
2
Machine hours Maintenance cost
High activity level 69000 96570
Low activity level 39000 62670
Change 30000 33900
Variable cost element 1.13 =33900/30000
Fixed cost element 18600 =96570-(69000*1.13)
Y = 18600 + 1.13 X
3
Variable cost per
machine hour
Fixed cost
Utilities cost 1.10
Supervisory salaries cost 46000
Maintenance cost 1.13 18600
Total overhead cost 2.23 64600
Y = 64600 + 2.23 X
4
Total overhead costs 162720 =64600+(44000*2.23)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours Total Overhead Cost   September 112,800 $ 781,512   October 89,200 $ 662,568   November 157,200 $ 1,005,288   December 165,000 $ 1,044,600 Assume that the overhead cost above consists of utilities, supervisory salaries, depreciation, and maintenance. The breakdown of these costs at the 89,200-machine-hour level of activity in October is as follows:   Utilities (variable) $ 233,704   Supervisory salaries       and depreciation (fixed) 172,000   Maintenance (mixed)      256,864   Total overhead...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 198,260 May 42,000 $ 172,460 June 62,000 $ 224,060 July 72,000 $ 249,860 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 58,800 Supervisory salaries (fixed) 49,000 Maintenance (mixed) 64,660 Total overhead cost $ 172,460 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 217,820 May 38,000 $ 190,420 June 58,000 $ 245,220 July 68,000 $ 272,620 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 70,000 Maintenance (mixed) 63,420 Total overhead cost $ 190,420 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 199,940 May 38,000 $ 172,640 June 58,000 $ 227,240 July 68,000 $ 254,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 54,000 Maintenance (mixed) 61,640 Total overhead cost $ 172,640 Nova Company’s...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 51,000 $ 181,360 May 41,000 $ 157,760 June 61,000 $ 204,960 July 71,000 $ 228,560 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) $ 53,300 Supervisory salaries (fixed) 48,000 Maintenance (mixed) 56,460...
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 3000 machine-hours. Manufacturing overhead costs...
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 3000 machine-hours. Manufacturing overhead costs were incurred as follows: $18000.....Utilities (a variable cost) $35300.....Maintenance (a mixed cost) $21000......Supervisor salaries (a fixed cost) $74300....Total overhead in March Total overhead in April was $87050 and machine-hours in April was 4500. Do not enter expenses as negative numbers. 1. How much of the April overhead must have been for Utilities? 2. How much of the April overhead must have been for Maintenance?
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 2900 machine-hours. Manufacturing overhead costs...
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 2900 machine-hours. Manufacturing overhead costs were incurred as follows: $14500.....Utilities (a variable cost) $35050..... Maintenance (a mixed cost) $18000...... Supervisor salaries (a fixed cost) $67550.... Total overhead in March Total overhead in April was $89400 and machine-hours in April was 5200. Do not enter expenses as negative numbers. 1. How much of the April overhead must have been for Utilities? 2. How much of the April overhead must have...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High Direct labor-hours 52,800 70,400 Total factory overhead costs $ 286,620 $ 328,860 The factory overhead costs above consist of indirect materials, rent, and...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,800 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,800 machine-hours Variable overhead costs: Supplies $ 22,040 Indirect labor 36,860 Fixed overhead costs: Supervision 16,900 Utilities 7,200 Depreciation 8,200 Total overhead cost $ 91,200 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 3,700 machine-hours rather than 3,800 machine-hours?
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 2,600 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 2,600 machine-hours Variable overhead costs: Supplies $ 11,960 Indirect labor 22,100 Fixed overhead costs: Supervision 15,600 Utilities 6,000 Depreciation 7,000 Total overhead cost $ 62,660 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 2,500 machine-hours rather than 2,600 machine-hours? Multiple Choice $60,750 $60,250 $61,350 $62,660 . Petrus Framing's cost...