Question

Under activity-based costing, which of the following are NOT considered a batch level activity: A) Machine...

Under activity-based costing, which of the following are NOT considered a batch level activity:

A) Machine setups

B) Production scheduling

C) Rent on factory building

D) Product testing

E) Materials receipts

Homework Answers

Answer #1

The correct answer is c - Rent on factory building

Batch level activities are costs incurred every time a batch of units or products are produced.

Machine setups, Poduction scheduling, Product testing, Materials receipts are those activities which will occur at the time of production of goods

Rent on a factory building has to be incurred irrespective of production and doesn't have impact on the batch of a goods under ABC method of costing

Hence rent of factory building is NOT considered a batch level activity.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Under activity-based costing, unit-, batch-, and product-level manufacturing overhead costs are A : excluded from estimates...
Under activity-based costing, unit-, batch-, and product-level manufacturing overhead costs are A : excluded from estimates of product cost.   B : excluded from inventory costing. C : included in selling and administrative costs. D : included in estimates of product cost.
Angara Corporation uses activity-based costing to determine product costs for external financial reports. The company has...
Angara Corporation uses activity-based costing to determine product costs for external financial reports. The company has provided the following data concerning its activity-based costing system: Activities (and Activity Measures) Estimated Overhead Cost Machine related (machine-hours) $268,400 Batch setup (setups) $279,300 General factory (direct labour-hours) $192,000 Expected Activity Activities Product X Product Y Total Machine related 4,500 6,500 11,000 Batch setup 9,000 1,500 10,500 General factory 3,500 6,500 10,000 Assuming that actual activity turns out to be the same as expected...
Which of the options is considered a batch-level activity? a. Machine set-up b. Warehouse costs c....
Which of the options is considered a batch-level activity? a. Machine set-up b. Warehouse costs c. Direct labor d. Preparing the annual budget Williamson Limited is expecting to invest in equipment that cost $120,000. The equipment has an 8-year life and no salvage value. Williamson uses straight-line depreciation. The equipment has a payback period of 5 years. The accounting rate of return is closest to a. 7.8%. b. 6.25%. c. 7.5%. d. 5%.
Rustafson Corporation is a diversidied manufacturer of consumer goods, The company's activity-based costing system has the...
Rustafson Corporation is a diversidied manufacturer of consumer goods, The company's activity-based costing system has the following seven activity cost pools: Activity cost pool estimated overhead cost expected activity labor-related $21,200 5,000 direct labor-hours Machine-related $2,000 8,000 machine-hours Machine setups $48,000 1,000 setups Production orders $9,800 200 orders Product testing $22,800 600 tests Packaging $64,600 3,800 packages General factory $56,000 5,000 direct labor-hours Required: 1.Compute the activity rate for each activity cost pool.(Round your answer to 2 decimal places.) Activity...
You are considering adopting an activity based costing model in your organization. Two activity pools are...
You are considering adopting an activity based costing model in your organization. Two activity pools are machine setup costing $30,000 and material moves costing $45,000. The measure for each is the number of occurrences which are 200 and 450 for machine setups and material moves, respectively. Product XJ500 requires 25 setups and 40 material moves. What is the per unit ABC cost assuming 100 units produced? a. $450.00 b. $115.38 c. $77.50 d. $90.45
1. Activity Cost Pool Activity Measure Estimated Overhead Costs Expected Activity Machine Setup Number of Setups...
1. Activity Cost Pool Activity Measure Estimated Overhead Costs Expected Activity Machine Setup Number of Setups                                         20,000                                        50 Special Processing Machine Hours                                       200,000                                  8,000 General Factory Direct labor Hours                                       250,000                               12,500 Calculate the activity rate for the following: Machine Setup: ____________ Special Processing: ____________ General Factory: ____________ 2. Product A Product B Product C Direct Labor Costs $    40,000.00 $ 190,000.00 $ 50,000.00 Direct Materials $ 100,000.00 $ 120,000.00 $ 60,000.00 Number of Setups...
ack Inc. manufactures two products and uses an activity-based costing system. Jack currently classifies machine setup...
ack Inc. manufactures two products and uses an activity-based costing system. Jack currently classifies machine setup costs of $120,000 as batch-level. Product A Product B Units 50,000 75,000 Batches 100 400 Direct Materials $10 per unit $10 per unit Direct Labour $15 per unit $15 per unit What will be the effect on the unit cost of Product A if Jack classifies the machine setup costs as product-level? Select one: a. It will decrease by $0.72 b. It will increase...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Larner Corporation is a diversified manufacturer of industrial goods. The company's activity-based costing system contains the...
Larner Corporation is a diversified manufacturer of industrial goods. The company's activity-based costing system contains the following six activity cost pools and activity rates: Activity Cost Pool Activity Rates Labor-related $ 9.00 per direct labor-hour Machine-related $ 5.00 per machine-hour Machine setups $ 30.00 per setup Production orders $ 200.00 per order Shipments $ 160.00 per shipment General factory $ 5.00 per direct labor-hour    Cost and activity data have been supplied for the following products:    J78 B52 Direct...
Which of the following statements is true of activity-based costing? A) In activity-based costing, direct labor-hours...
Which of the following statements is true of activity-based costing? A) In activity-based costing, direct labor-hours is always the best allocation base to allocate all non-manufacturing indirect costs B)  The main advantage of activity-based costing over peanut-butter costing is the accurate distribution of all direct costs to the products. C)  Activity based costing broadly averages or spreads the cost of resources uniformly to cost objects such as products or services. D)  Activity based costing is more useful to companies with high product diversity...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT