Question

ack Inc. manufactures two products and uses an activity-based costing system. Jack currently classifies machine setup...

ack Inc. manufactures two products and uses an activity-based costing system. Jack currently classifies machine setup costs of $120,000 as batch-level.

Product A

Product B

Units

50,000

75,000

Batches

100

400

Direct Materials

$10 per unit

$10 per unit

Direct Labour

$15 per unit

$15 per unit

What will be the effect on the unit cost of Product A if Jack classifies the machine setup costs as product-level?

Select one:

a. It will decrease by $0.72

b. It will increase by $0.48

c. It will increase by $0.72

d. There will be no effect

Homework Answers

Answer #1

Answer:

Correct answer is:

c. It will increase by $0.72

Explanation:

Setup cost per unit of Product A when machine setup costs are classified as batch-level cost:

Number of batches = 100 + 400 = 500

Activity rate for setup cost = 120000 / 500= $240 per batch

Setup cost assigned to Product A = 240 * 100 = $24,000

Setup cost per unit of Product A = 24000 / 50000 = $0.48

Setup cost per unit of Product A when machine setup costs are classified as Product level cost:

Number of products = 2

Activity rate for setup cost = 120000 / 2= $60,000 per product

Setup cost assigned to Product A = 60000 * 1 = $60,000

Setup cost per unit of Product A = 60000 / 50000 = $1.20

Increase in setup cost per unit of Product A = 1.20 - 0.48 = $0.72

Increase in setup cost per unit of Product A = $0.72

As such option c is correct and other options a, b, and d are incorrect.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Roti Boy Inc. makes 2 distinct products and uses an activity-based (ABC) costing system. Some of...
Roti Boy Inc. makes 2 distinct products and uses an activity-based (ABC) costing system. Some of the cost information for the company is as follows: Product A Product B Total units produced 100,000 50,000 Number of units per batch 2, 000 5, 000 Batch-level Overhead Costs: Total batch level overhead cost: $60,000. Batch level overhead cost is made up entirely of machine set up costs The machine set up cost per batch is the same for both Product A and...
Goodwin Co. manufactures two products: R and W. The company uses activity-based costing to apply manufacturing...
Goodwin Co. manufactures two products: R and W. The company uses activity-based costing to apply manufacturing overhead costs to products. The cost pools and related estimated overhead costs for 20x3 are as follows: Activity Cost Pool Activity measure Overhead cost Assembly Number of direct labour hours $35194 Inspection Number of inspections 159307 Product support # of engineers 252107 The expected activity measures for the manufacturing of product R in 20x3 are: 141 direct labour hours, 4901 inspections, and 2 engineer(s)....
Goodwin Co. manufactures two products: R and W. The company uses activity-based costing to apply manufacturing...
Goodwin Co. manufactures two products: R and W. The company uses activity-based costing to apply manufacturing overhead costs to products. The cost pools and related estimated overhead costs for 20x3 were as follows: Activity Cost Pool Activity measure Overhead cost Purchase orders Number of purchase orders $34475 Assembly Number of direct labour hours 152143 The expected activity measures for the manufacturing product R in 20x3 were: 228 purchase orders and 4560 direct labour hours. The expected activity measures for the...
Angara Corporation uses activity-based costing to determine product costs for external financial reports. The company has...
Angara Corporation uses activity-based costing to determine product costs for external financial reports. The company has provided the following data concerning its activity-based costing system: Activities (and Activity Measures) Estimated Overhead Cost Machine related (machine-hours) $268,400 Batch setup (setups) $279,300 General factory (direct labour-hours) $192,000 Expected Activity Activities Product X Product Y Total Machine related 4,500 6,500 11,000 Batch setup 9,000 1,500 10,500 General factory 3,500 6,500 10,000 Assuming that actual activity turns out to be the same as expected...
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana...
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of its overhead. Additional information about overhead follows. Activity Cost Driver Setting up machines $ 18,750 25 batches Inspecting components $ 5,200 5,200 parts Providing utilities $ 10,400 5,200 machine hours Overhead has...
12) Lakeside Inc. manufactures four lines of remote control boats and uses activity-based costing to calculate...
12) Lakeside Inc. manufactures four lines of remote control boats and uses activity-based costing to calculate product cost. Activity Cost Pools Estimated Total Cost Estimated Cost Driver Machining $ 317,000 13,900 machine hours Setup 61,000 250 batches Quality control 85,000 880 inspections Suppose the Speedy boat requires 2,300 machine hours, 94 batches, and 260 inspections. Using the activity rates, determine the amount of overhead assigned to the Speedy product line. (Round intermediate calculations to 2 decimal places and your final...
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana...
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of its overhead. Additional information about overhead follows. Activity Cost Driver Setting up machinfes $ 24,030 27 batches Inspecting components $ 4,800 4,800 parts Providing utilities $ 9,600 4,800 machine hours Overhead has...
Activity-Based Costing HealthTec Equipment Company manufactures stationary bicycles and treadmills. The products are produced in the...
Activity-Based Costing HealthTec Equipment Company manufactures stationary bicycles and treadmills. The products are produced in the Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $33 per machine hour (mh) Assembly $12 per direct labor hour (dlh) Setup $50 per setup Inspecting $30 per inspection Production scheduling $14 per production order Purchasing $8 per purchase...
Addleman Corporation has an activity-based costing system with three activity cost pools--Processing, Supervising, and Other. In...
Addleman Corporation has an activity-based costing system with three activity cost pools--Processing, Supervising, and Other. In the first stage allocations, costs in the two overhead accounts, equipment expense and indirect labor, are allocated to the three activity cost pools based on resource consumption. Data used in the first stage allocations follow: Overhead costs: Equipment expense $ 73,000 Indirect labor $ 1,000 Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Processing Supervising Other Equipment expense 0.20 0.10 0.70...
Activity-Based Department Rate Product Costing and Product Cost Distortions Big Sound Inc. manufactures two products: receivers...
Activity-Based Department Rate Product Costing and Product Cost Distortions Big Sound Inc. manufactures two products: receivers and loudspeakers. The factory overhead incurred is as follows: Indirect labor $400,400 Subassembly Department 198,800 Final Assembly Department 114,800 Total $714,000 The activity base associated with the two production departments is direct labor hours. The indirect labor can be assigned to two different activities as follows: Activity Budgeted Activity Cost Activity Base Setup $138,600 Number of setups                               Quality control 261,800 Number of inspections                        Total...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT