Question

During February, Alexander Inc. worked on two jobs with the following data: Job 12 Job 13...

During February, Alexander Inc. worked on two jobs with the following data: Job 12 Job 13 Units in each order 100 units 200 units Units sold 100 units ---- Materials requisitioned $2,480 $1,970 Direct labor hours 820 hrs. 1,166 hrs. Direct labor cost $12,300 $17,490 Overhead is assigned on the basis of direct labor hours at a rate of $12. During February, Job 12 was completed and transferred to finished goods. Job 13 is the only unfinished job at the end of the month. Prepare the journal entries reflecting the completion of Job 12 and its eventual sale on account. The selling price is 160% of cost.

Homework Answers

Answer #1
Journal Entry- Alexander Inc.
Date Account Tittle & Explanation Debit Credit
Aug. 31 Finished Goods $24,620.00
Work In Process $24,620.00
To Record Completion Of Job12
Aug. 31 Account Receivable (24620*160%) $39,392.00
Sales Revenue $39,392.00
To Record Sales of Job-12
Aug. 31 Cost Of Goods Sold $24,620.00
              Finished Goods $24,620.00
To Record Cost Of Goods Sold for Job-12
Cost of Goods Sold for Job-12
Material Cost $2,480.00
Labour Cost $12,300.00
Manufacturign Overhead (12*820) $9,840.00
Total cost for Job12 $24,620.00
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Unit Cost, Ending Work in Process, Journal Entries During August, Pamell Inc. worked on two jobs....
Unit Cost, Ending Work in Process, Journal Entries During August, Pamell Inc. worked on two jobs. Data relating to these two jobs follow: Job 64 -Job 65 Units in each order 500----------- 1,000 Units sold 500 —(zero) Materials requisitioned--- $19,840 $15,760 Direct labour hours 900 1,260 Direct labour cost $17,100 $23,940 Overhead is assigned on the basis of direct labour hours at a rate of $37. During August, Job 64 was completed and transferred to Finished Goods. Job 65 was...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow:       Job 78       Job 79       Job 80 Units in each order 290   180         230   Units sold —   180         —   Materials requisitioned $1,740   $1,062         $2,507   Direct labor hours 319   198         345   Direct labor cost $3,509   $3,168         $3,312   Overhead is assigned on the basis of direct labor hours at a rate of $8.90 per...
The Manufacturing Department accepted Job 705 on February 29th to make 1,000 units.. To complete the...
The Manufacturing Department accepted Job 705 on February 29th to make 1,000 units.. To complete the job they requisitioned 2,100 metal sheets at $2.10 per sheet and 3,150 screws at $0.51 per screw. The cost driver that the Manufacturing Department is machine hours which are counted on a machine mounted counter. $4.52 is applied as overhead for each machine hour. Additionally, $425.00 of overhead is applied to each job due to setup and teardown. Direct labor is $25.20 per hour...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $16 per unit and 1,000 units for Job 42 at $24 per unit. During August, Prichard Company accumulated 600 hours of direct labor costs on Job 40...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q.
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is...
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is for 500 units, and Job 42 is for 200 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $18 per unit and 900 units for Job 42 at $20 per unit. During August, Darling Company accumulated 600 hours of direct labor costs on Job 40 and 1,100...
1. The overhead cost applied to a job during a period is recorded with a credit...
1. The overhead cost applied to a job during a period is recorded with a credit to Factory Overhead and a debit to: Multiple Choice Jobs Overhead Expense. Cost of Goods Sold. Finished Goods Inventory. Indirect Labor. Work in Process Inventory. 2. Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the...
London Ceramics makes custom ceramic tiles. During​ March, the company started and finished Job​ #266. Job​...
London Ceramics makes custom ceramic tiles. During​ March, the company started and finished Job​ #266. Job​ #266 consists of 3,500 ​tiles; each tile sells for $18. The​ company's records show the following direct materials were requisitioned for Job​ #266. Basic terra cotta​ tiles:   3,500 units at ​$4 per unit Specialty​ paint:   13 quarts at $10 per quart High gloss​ glaze: 12 quarts at $20 per quart Labor time records show the following employees worked on Job​ #266: Alice​ Cooper: 22...
London Ceramics makes custom ceramic tiles. During​ March, the company started and finished Job​ #266. Job​...
London Ceramics makes custom ceramic tiles. During​ March, the company started and finished Job​ #266. Job​ #266 consists of 3,500 ​tiles; each tile sells for $18. The​ company's records show the following direct materials were requisitioned for Job​ #266. Basic terra cotta​ tiles:  3,500 units at ​$4 per unit Specialty​ paint:  13 quarts at $10 per quart High gloss​ glaze: 12 quarts at $20 per quart Labor time records show the following employees worked on Job​ #266: Alice​ Cooper: 22...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT