Question

Job Costs At the end of August, Prichard Company had completed Jobs 40 and 42. Job...

Job Costs

At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 2,000 units.

The following data relate to these two jobs:

On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $16 per unit and 1,000 units for Job 42 at $24 per unit.

During August, Prichard Company accumulated 600 hours of direct labor costs on Job 40 and 800 hours on Job 42. The total direct labor was incurred at a rate of $12 per direct labor hour for Job 40 and $18 per direct labor hour for Job 42.

The predetermined factory overhead rate is $9.00 per direct labor hour.

a. Determine the balance on the job cost sheets for Jobs 40 and 42 at the end of August.

Job 40 $
Job 42 $

b. Determine the cost per unit for Jobs 40 and 42 at the end of August. If required, round your answers to the nearest cent.

Job 40 $
Job 42 $

Homework Answers

Answer #1

a) balance on job cost sheets for JOB 40 and JOB 42.

particulars JOB 40 JOB 42
Raw material requisition

4800

(300 units x $16)

24000

(1000 units x $24)

direct labour costs( given that 600 hours of direct labor costs on Job 40 and 800 hours on Job 42. direct labor was incurred at a rate of $12 per direct labor hour for Job 40 and $18 per direct labor hour for Job 42).

7200

(600hours x $12)

14400

(800hours x $18)

factory overheads (given that factory overhead rate is $9.00 per direct labor hour).

5400

($9 x 600hours)

7200

($9 x 800hours)

total cost 17,400 45,600

b) Cost per unit = total cost / no. of units produced.

PARTICULARS JOB 40 JOB 42
TOTAL COST 17,400 45,600
UNITS PRODUCED IN AUGUST 200 2000
COST PER UNIT $87 (17400/200) $22.8 (45600/2000)

HOPE THAT HELPED. PLEASE SHARE YOUR FEEDBACK . THANK YOU.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is...
At the end of August, Prichard Company had completed Jobs 40 and 42. Job 40 is for 200 units, and Job 42 is for 500 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 400 units for Job 40 at $10 per unit and 1,500 units for Job 42 at $14 per unit. During August, Prichard Company accumulated 400 hours of direct labor costs on Job 40 and 1,200...
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is...
At the end of August, Darling Company had completed Jobs 40 and 42. Job 40 is for 500 units, and Job 42 is for 200 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 300 units for Job 40 at $18 per unit and 900 units for Job 42 at $20 per unit. During August, Darling Company accumulated 600 hours of direct labor costs on Job 40 and 1,100...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job...
Job Costs At the end of August, Kaye Company had completed Jobs 40 and 42. Job 40 is for 1,000 units, and Job 42 is for 200 units. The following data relate to these two jobs: On August 4, raw materials were requisitioned for production as follows: 200 units for Job 40 at $20 per unit and 1,400 units for Job 42 at $16 per unit. During August, Kaye Company accumulated 300 hours of direct labor costs on Job 40...
At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is...
At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 200 units, and Job 51 is for 2,000 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 600 units for Job 50 at $24 per unit and 900 units for Job 51 at $18 per unit. During April, Kaye Company accumulated 200 hours of direct labor costs on Job 50 and 400...
At the end of April, Ingram Company had completed Jobs 50 and 51. Job 50 is...
At the end of April, Ingram Company had completed Jobs 50 and 51. Job 50 is for 1,000 units, and Job 51 is for 500 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 500 units for Job 50 at $18 per unit and 1,400 units for Job 51 at $18 per unit. During April, Ingram Company accumulated 400 hours of direct labor costs on Job 50 and 700...
1. Carrothers Company estimates that total factory overhead costs will be $960,000 for the year. Direct...
1. Carrothers Company estimates that total factory overhead costs will be $960,000 for the year. Direct labor hours are estimated to be 80,000. a. For Carrothers Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. ___________ per direct labor hour b. During August, Carrothers Company accumulated 4,300 hours of direct labor costs on Job 50 and 5,100 hours on Job 56. Determine the amount of factory overhead applied to Jobs 50 and 56 in...
Direct Labor Costs During August, Hatch Company accumulated 610 hours of direct labor costs on Job...
Direct Labor Costs During August, Hatch Company accumulated 610 hours of direct labor costs on Job 40 and 890 hours on Job 42. The total direct labor was incurred at a rate of $20 per direct labor hour for Job 40 and $25 per direct labor hour for Job 42. Journalize the entry to record the flow of labor costs into production during August.
Applying Factory Overhead Keenan Company estimates that total factory overhead costs will be $144,000 for the...
Applying Factory Overhead Keenan Company estimates that total factory overhead costs will be $144,000 for the year. Direct labor hours are estimated to be 9,000. a. For Keenan Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. If required, round your answer to two decimal places. $ per direct labor hour b. During August, Keenan Company accumulated 850 hours of direct labor costs on Job 40 and 890 hours on Job 42. Determine the...
SHIM & SHS Company uses a job-order costing system. The company applies manufacturing overhead to jobs...
SHIM & SHS Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on labor-hours. Beginning of the year, manufacturing overhead and labor-hours were estimated at $160,000 and 40,000 hours respectively, for the year. In June, Job #100 was completed. Materials costs on the job totaled $3,000 and labor costs totaled $4,800 at $6 per hour. Job #100 required 800 labor hours and 1,000 machine hours. At the end of the...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT