Question

1. The overhead cost applied to a job during a period is recorded with a credit...

1. The overhead cost applied to a job during a period is recorded with a credit to Factory Overhead and a debit to:

Multiple Choice

Jobs Overhead Expense.

Cost of Goods Sold.

Finished Goods Inventory.

Indirect Labor.

Work in Process Inventory.

2. Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the month, but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred. What is the balance in the Work in Process account at the end of September relative to Job A3B?

Multiple Choice

$5,500

$11,500

$6,500

$9,500

$14,500

3.

Beginning WIP 4,500
Direct materials 47,100
Direct labor 29,600
Applied Overhead 15,800
Total Manufacturing Costs 97,000
To Finished Goods ?
Ending WIP 8,900


The cost of units transferred to finished goods is:

Multiple Choice

$97,000.

$105,900.

$88,100.

$95,200.

$92,500.

4. Equivalent units of production are equal to:

Multiple Choice

The number of units that could have been started and completed given the costs incurred during the period.

The number of finished units actually produced during a period.

The number of units started into the process during a period.

The number of units still in process at the end of a period.

Physical units that were started and completed during a period.

5. K Company estimates that overhead costs for the next year will be $2,970,000 for indirect labor and $990,000 for factory utilities. The company uses direct labor hours as its overhead allocation base. If 99,000 direct labor hours are planned for this next year, how much overhead would be assigned to a product requiring 4 direct labor hours?

Multiple Choice

$40.00

$30.00

$160.00

$120.00

None of the choices

Homework Answers

Answer #1

1) Work in Progress Inventory

2) $ 14,500

Work in Progress = Direct Material + direct Labor + Overhead = $2,500 + $4,000 + $4,000*200%

= $14,500

3) $88,100

Cost of goods transferred to finished goods

= Beginnig WIP + Direct material + Direct labor + Overhead - Closing WIP

= $4,500 + $47,100 + $29,600 +$15,800 - $8,900

=$88,100

4) The number of units that could have been started and completed given the costs incurred during the period.

5) $160.00

Overhead allocation per hour = ($2,970,000 +$990,000) / 99,000 = $40 per hour

for 4 direct labour hours = 4 * $40 = $160

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Job A3B was ordered by a customer on September 25. During the month of September, Jaycee...
Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the month, but needed an additional $3,000 of direct materials and additional direct labor of $6,500 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred....
Job A3B was ordered by a customer on September 25. During the month of September, Jaycee...
Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,300 of direct materials and used $4,800 of direct labor. The job was not finished by the end of the month, but needed an additional $3,800 of direct materials and additional direct labor of $8,100 to finish the job in October. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost incurred....
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct...
Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 93,000 and estimated factory overhead is $511,500. The following information is for September of the current year. Job A was completed during September, and Job B was started but not finished September 1, inventories        Materials inventory $ 8,400    Work-in-process inventory (All Job A) 33,000    Finished goods...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Job 86 Job 87 Direct materials $4,800 $1,600 Direct labor 1,200 3,000 Applied overhead 888 2,220 Balance, March 1 $6,888 $6,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 133,000 and estimated factory overhead is $784,700. The following information is for September. Job X was completed during September, while Job Y was started but not finished. September 1, inventories:     Materials $24,000     Work-in-process (All Job X) 53,400     Finished goods 105,600 Materials purchases $157,000 Direct materials requisitioned:     Job...
Overhead applied to production Problem: ABC Corp. uses job order costing. Overhead applied to production is...
Overhead applied to production Problem: ABC Corp. uses job order costing. Overhead applied to production is at a predetermined rate of 80% based on direct labor costs. The following accounts appear in the general ledger of the company for the month of September 2020 Debits Work in process, September 1              $60,000 Direct Materials 120,000 Direct Labor 100,000 Factory overhead 80,000 On September 30, 2020 finished goods completed from work in process cost $320,000. Job No. 1 was the only...
10-Dazzle, Inc. produces beads for jewelry making use. The following information summarizes production operations for June....
10-Dazzle, Inc. produces beads for jewelry making use. The following information summarizes production operations for June. The journal entry to record June production activities for direct material usage is: Direct materials used $ 90,000 Direct labor used 163,000 Predetermined overhead rate (based on direct labor) 155 % Goods transferred to finished goods 435,000 Cost of goods sold 447,000 Credit sales 813,000 Multiple Choice Debit Work in Process Inventory $90,000; credit Raw Materials Inventory $90,000. Debit Work in Process Inventory $90,000;...
Morrow Corporation had only one job in process during May—Job X32Z—and had no finished goods inventory...
Morrow Corporation had only one job in process during May—Job X32Z—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below:         Job X32Z Beginning balance $ 5,000 Charged to the job during May Direct materials $ 8,000 Direct labor $ 2,000 Manufacturing overhead applied $ 4,000 Units completed 100 Units in process at the end of May 0 Units sold during May 40 In May, overhead...
Morrow Corporation had only one job in process during May—Job X32Z—and had no finished goods inventory...
Morrow Corporation had only one job in process during May—Job X32Z—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below:         Job X32Z Beginning balance $ 5,800 Charged to the job during May Direct materials $ 9,100 Direct labor $ 2,800 Manufacturing overhead applied $ 4,800 Units completed 180 Units in process at the end of May 0 Units sold during May 80 In May, overhead...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT