Answer :-
B- $16,913
.
Explanations :-
Direct Material | Amount | ||
Basic terra cotta tiles | 3500 unit at $4 per unit | $14,000 | |
Specially Paint | 13 Quarts at $10 per quarts | $130 | |
High Gloss glaze | 12 Quarts at $20 per quarts | $240 | $14,370 |
Direct Labour | |||
Alice Cooper | 22 hours at $30 per hour | $660 | |
Mathew Kline | 21 hours $18 per hour | $378 | $1,038 |
Manufacturing Overhead | total labour hour (22+21) × $35 per hour | $1,505 | $1,505 |
Total Job Cost |
Total Job Cost = Total Direct Material amount + Total Direct Labour Amount + Total Manifacturing overhead amount
Total Job Cost = $14,370 + $1,038 + $1,505
Total Job Cost = $16,913