Question

Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...

Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: During the year, the following actual amounts were experienced:

Number of direct labor hours = 6720

Direct labor cost = 67,200

Overhead cost = 50,400

During the year the following actual amounts were experienced

number of direct labor hours = 6045

Direct labor incurred = 66,495

Overhead incurred = 50,500

1. Should EcoScape use process costing or job-order costing?

- Select your answer -Process costingJob-order costingItem 1

2. If EcoScape uses a normal costing system and overhead is applied on the basis of direct labor hours,

What is the overhead rate? Round your answer to the nearest cent.

$ per direct labor hour

What is the average actual wage rate?

$ per direct labor hour

What is the cost of an installation that takes $3,500 of direct materials and 20 direct labor hours?

$

Homework Answers

Answer #1

Solution 1:

As EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state and each job is different, requiring different materials and labor for installing the systems, therefore Ecoscape should use Job order costing rather than process costing. As each job requries different labor and material therefore job pricing should be done on the basis of estimated cost to be incurred on particular job. Therefore job order costing should be used.

Solution 2:

Overhead rate = Estimated overhead / Estimated direct labor hours

= $50,400 / 6720 = $7.50 per hour

Average actual wage rate = Actual direct labor / Actual direct labor hours

= $66,495 / 6045 = $11 per hour

Cost of an installation = Direct material cost + Direct labor cost + Applied overhead

= $3,500 + 20*$11 + 20*$7.50

= $3,870

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,870 Direct labor cost $82,440 Overhead cost $55,647 During the year, the following actual amounts were experienced: Number of direct labor hours 6,130 Direct labor incurred $79,690 Overhead...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $135,000 for the year and the estimated direct labor hours were 15,000 hours. In May, Job #378 was completed. Direct materials totaled $8,500. Total labor costs were $14,000 at $16 per hour. At the end of the year, it was determined that the company worked 16,000 direct labor...
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
1.Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant...
1.Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
A company which uses a job-costing system, had two jobs in process at the start of...
A company which uses a job-costing system, had two jobs in process at the start of February 2018: Job no. J6 with a cost of $110,000 and job no. F1 with a cost of $22,000. The following information is available: The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,366,000 and 102,000 hours, respectively. The company worked on four jobs during February. Direct materials used, direct...