Question

A company has the following information for Job Alpha during July: Units produced              257 Actual...

  1. A company has the following information for Job Alpha during July:

Units produced

             257

Actual materials used

          1,722

lbs.

Actual materials cost

$         5.85

per lb.

Actual labor hours incurred

             771

Actual labor rate

$      14.25

per hour

Work in process, July 1

$      4,000

Work in process, July 31

$             -  

The company applies manufacturing overhead to jobs based on direct labor hours.

Additional information for the company in July is as follows:

Total estimated labor hours

          2,170

Standard materials per unit

7

lbs.

Standard materials cost

$         5.50

per lb.

Standard labor hours per unit

2.80

Standard labor rate

$      15.00

per hour

Standard variable overhead

$         3.00

per labor hour

Standard fixed overhead

$         2.00

per labor hour

    *based on 35,000 labor hours

Actual total output in units

             755

Actual total labor hours

          2,454

Actual variable overhead

$         3.40

per labor hour

Actual total fixed overhead

$      4,040

  1. Calculate the company’s total estimated overhead for July (2 points):
  2. If the company uses a normal costing system, calculate the costs incurred by Job Alpha in July (3 points):
  3. Calculate the total cost of Job Alpha using a normal costing system:
  4. Calculate the materials flexible budget for Job Alpha in July:

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per...
A manufactured product has the following information for August. Standard Actual Direct materials 2 lbs. per unit @ $12.50 per lb. Direct labor 0.5 hours per unit @ $96 per hour Overhead $132 per direct labor hour Units manufactured 16,000 Total manufacturing costs $ 2,216,400 (1) Compute the standard cost per unit. (2) Compute the total budgeted cost for production in August. (3) Compute the total cost variance for August. (Indicate the effect of each variance by selecting for favorable,...
The following data relates to Potawatomi Corporation's operations for the month. Potawatomi produced 8,500 units and...
The following data relates to Potawatomi Corporation's operations for the month. Potawatomi produced 8,500 units and the normal monthly capacity is 20,000 direct labor hours. Standard Unit Costs Total Actual Costs Direct Material:          Standard (5 lbs. @ $2.10/lb.) $10.50          Actual (39,000 lbs. @ $2.20/lb.) $85,800 Direct Labor:         Standard (2 hrs. @ $12/hr.) $24.00         Actual (18,000 hrs. @ $11.90/hr.) $214,200 Variable Overhead:         Standard (2 hrs. @ $4.00/hr.) $8.00         Actual $69,700                Total $42.50 $369,700 Calculate...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $66,000 and 22,000 hours, respectively. In June, Job #461 was completed. Materials costs on the job totaled $4,923 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked 23,975 direct...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...
Required information [The following information applies to the questions displayed below.] A manufactured product has the...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 7 lbs. @ $8 per lb. 62,900 lbs. @ $8.10 per lb. Direct labor 3 hrs. @ $17 per hr. 26,400 hrs. @ $17.50 per hr. Overhead 3 hrs. @ $13 per hr. $ 352,500 Units manufactured 8,900 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance...
Malkovich Company uses a standard costing system. The following information pertains to direct materials for the...
Malkovich Company uses a standard costing system. The following information pertains to direct materials for the month of July: Standard price per lb. $18.00 Actual purchase price per lb. $16.50 Quantity purchased 3,100 lbs. Quantity used 2,950 lbs. Standard quantity allowed for actual output 3,000 lbs. Actual output 1,000 units Malkovich Company reports its material price variances at the time of purchase. What is the standard quantity of direct materials per unit for Malkovich Company?
SHIM & SHS Company uses a job-order costing system. The company applies manufacturing overhead to jobs...
SHIM & SHS Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on labor-hours. Beginning of the year, manufacturing overhead and labor-hours were estimated at $160,000 and 40,000 hours respectively, for the year. In June, Job #100 was completed. Materials costs on the job totaled $3,000 and labor costs totaled $4,800 at $6 per hour. Job #100 required 800 labor hours and 1,000 machine hours. At the end of the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT