Question

Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...

Characteristics of Production Process, Cost Measurement

Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year:

Number of direct labor hours 6,720
Direct labor cost $67,200
Overhead cost $50,400

During the year, the following actual amounts were experienced:

Number of direct labor hours 6,045
Direct labor incurred $66,495
Overhead incurred $50,500

Vince Melders, owner of EcoScape, noticed that the watering systems for many houses in a local subdivision had the same layout and required virtually identical amounts of prime cost. Vince met with the subdivision builders and offered to install a basic watering system in each house. The idea was accepted enthusiastically, so Vince created a new company, Irrigation Specialties, to handle the subdivision business. In its first three months in business, Irrigation Specialties experienced the following:

June July August
Number of systems installed 68 88 108
Direct materials used $20,400 $26,400 $32,400
Direct labor incurred $13,600 $17,600 $21,600
Overhead $12,240.00 $12,320.00 $12,960.00

Required:

1. Should Irrigation Specialties use process costing or job-order costing?

Job-order costing

2. If Irrigation Specialties uses an actual costing system, what is the cost of a single system installed in June? In July? In August? Round your answers to the nearest dollar.

June $ per system
July $ per system
August $ per system

3. Now assume that Irrigation Specialties uses a normal costing system. Estimated overhead for the year is $54,000, and estimated production is 600 watering systems. What is the predetermined overhead rate per system?

$ per system installed

What is the cost of a single system installed in June? In July? In August?

June $ per system
July $ per system
August $ per system

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,720 Direct labor cost $67,200 Overhead cost $50,400 During the year, the following actual amounts were experienced: Number of direct labor hours 6,045 Direct labor incurred $66,495 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,870 Direct labor cost $82,440 Overhead cost $55,647 During the year, the following actual amounts were experienced: Number of direct labor hours 6,130 Direct labor incurred $79,690 Overhead...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn...
Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: During the year, the following actual amounts were experienced: Number of direct labor hours = 6720 Direct labor cost = 67,200 Overhead cost = 50,400 During the year the following actual amounts were...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $135,000 for the year and the estimated direct labor hours were 15,000 hours. In May, Job #378 was completed. Direct materials totaled $8,500. Total labor costs were $14,000 at $16 per hour. At the end of the year, it was determined that the company worked 16,000 direct labor...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
Parker Company has a job-order costing system and uses a pre-determined overhead rate based on direct...
Parker Company has a job-order costing system and uses a pre-determined overhead rate based on direct labor hours to apply manufacturing overhead to jobs. At the beginning of the year, manufacturing overhead and direct labor hours for the year were estimated at $50,000 and 25,000 hours respectively. In June, Job #461 was started, completed, and sold to a customer. Materials cost on the job totaled $4,000, and labor costs were $5 per hour and totaled $1,500. Sales commissions incurred on...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $66,000 and 22,000 hours, respectively. In June, Job #461 was completed. Materials costs on the job totaled $4,923 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked 23,975 direct...
1.Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant...
1.Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT