Question

Edwards Company contracted on 4/1/17 to construct a building for $4,800,000. The project was completed in...

Edwards Company contracted on 4/1/17 to construct a building for $4,800,000. The project was completed in 2019. Additional data follow: 2017 2018 2019 Costs incurred to date $1,120,000 $2,700,000 $3,800,000 Estimated cost to complete 2,080,000 900,000 — Billings to date 1,000,000 3,800,000 4,800,000 Collections to date 800,000 2,600,000 4,400,000 Instructions (a) Calculate the income recognized by Edwards under the percentage-of-completion method of accounting in each of the years 2017, 2018, and 2019. (b) Prepare all necessary entries for the year 2018. (c) Present the balance sheet disclosures at December 31, 2018. Proper headings or subheadings must be indicated.

Homework Answers

Answer #1

A)

Particulars Calculation Amount($)
Gross Profit Recognized in 2017 $4800000*($1120000/($1120000+$2080000)) - $1120000 560000
Gross Profit Recognized in 2018 ($4800000*($2700000/($2700000+$900000)) - $2700000) - $560000 340000
Gross Profit Recognized in 2019 $4800000 - $3800000 - $560000 - $340000 100000

B) Journal Entries :-

S No. Particulars Debit($) Credit($)
1) Construction in Process A/c Dr. 1580000
To Accounts Payables A/c ($2700000-$1120000) 1580000
(To record cost of contruction)
2) Contract Receivable A/c Dr.($3800000-$1000000) 2800000
To Progressive Billing A/c 2800000
3) Cash A/c Dr. ($2600000 - $800000) 1800000
To Contract Receivable A/c 1800000
4) Contruction Expense A/c Dr. 1580000
Contruction in Process A/c Dr. 340000
To Revenue from Contract A/c 1920000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0- Billings 1,200,000 4,100,000 4,300,000 Instructions(a) Using...
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date                                                   Expenditures March 1, 2019                                  $   1,200,000 May 1, 2019                                          1,680,000 August 1, 2019                                      3,000,000 September 30, 2019                              4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
Problem 18-10 On March 1, 2020, Pearl Construction Company contracted to construct a factory building for...
Problem 18-10 On March 1, 2020, Pearl Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,360,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,615,800 $2,633,000 $2,041,200 Estimated costs to complete the contract at 12/31 3,764,200 2,041,200...