Question

Problem 18-10 On March 1, 2020, Pearl Construction Company contracted to construct a factory building for...

Problem 18-10

On March 1, 2020, Pearl Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,360,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below:

2020

2021

2022

Contract costs incurred during the year $2,615,800 $2,633,000 $2,041,200
Estimated costs to complete the contract at 12/31 3,764,200 2,041,200 –0–
Billings to Fabrik during the year 3,230,000 3,500,000 1,630,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2020

Profit / (Loss) Recognized in 2020Costs IncurredPercent CompleteRevenue RecognizedEstimated Total CostsCosts to date (12/31/20)Estimated Costs to Complete

$

Profit / (Loss) Recognized in 2020Percent CompleteEstimated Total CostsRevenue RecognizedCosts to date (12/31/20)Estimated Costs to CompleteCosts Incurred

    Profit / (Loss) Recognized in 2020    Percent Complete    Revenue Recognized    Estimated Costs to Complete    Estimated Total Costs    Costs Incurred    Costs to date (12/31/20)    

$

Profit / (Loss) Recognized in 2020Costs to date (12/31/20)Estimated Total CostsCosts IncurredEstimated Costs to CompletePercent CompleteRevenue Recognized

%

Costs to date (12/31/20)Estimated Costs to CompleteEstimated Total CostsPercent CompleteRevenue RecognizedCosts IncurredProfit / (Loss) Recognized in 2020

$

Percent CompleteCosts to date (12/31/20)Costs IncurredProfit / (Loss) Recognized in 2020Estimated Costs to CompleteRevenue RecognizedEstimated Total Costs

Percent CompleteEstimated Costs to CompleteRevenue RecognizedCosts IncurredProfit / (Loss) Recognized in 2020Costs to date (12/31/20)Estimated Total Costs

$

2021

Estimated Total CostsPercent CompleteRevenue Recognized in 2021Profit / (Loss) Recognized in 2020Costs Incurred in 2021Costs to date (12/31/21)Estimated Costs to Complete

$

Estimated Costs to CompleteEstimated Total CostsRevenue Recognized in 2021Costs to date (12/31/21)Costs Incurred in 2021Profit / (Loss) Recognized in 2020Percent Complete

    Estimated Costs to Complete    Costs to date (12/31/21)    Estimated Total Costs    Revenue Recognized in 2021    Costs Incurred in 2021    Percent Complete    Profit / (Loss) Recognized in 2020    

$

Costs to date (12/31/21)Estimated Total CostsEstimated Costs to CompletePercent CompleteRevenue Recognized in 2021Costs Incurred in 2021Profit / (Loss) Recognized in 2020

%

Revenue Recognized in 2021Percent CompleteEstimated Total CostsCosts Incurred in 2021Estimated Costs to CompleteProfit / (Loss) Recognized in 2020Costs to date (12/31/21)

$

Profit / (Loss) Recognized in 2020Costs Incurred in 2021Estimated Costs to CompleteCosts to date (12/31/21)Estimated Total CostsPercent CompleteRevenue Recognized in 2021

    Costs Incurred in 2021    Estimated Total Costs    Revenue Recognized    Costs to date (12/31/21)    Percent Complete    Profit / (Loss) Recognized in 2021    Estimated Costs to Complete    

$

2022

Total Profit on ContractTotal Costs IncurredProfit Previously RecognizedProfit / (Loss) Recognized in 2022Total Revenue Recognized

$

Total Revenue RecognizedTotal Costs IncurredTotal Profit on ContractProfit Previously RecognizedProfit / (Loss) Recognized in 2022

Total Costs IncurredProfit Previously RecognizedTotal Revenue RecognizedTotal Profit on ContractProfit / (Loss) Recognized in 2022

AddLess

:

Total Profit on ContractTotal Revenue RecognizedProfit Previously RecognizedProfit / (Loss) Recognized in 2022Total Costs Incurred

Total Revenue RecognizedTotal Profit on ContractTotal Costs IncurredProfit / (Loss) Recognized in 2022Profit Previously Recognized

$

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2020 $
2021 $
2022 $
Click if you would like to Show Work for this question:

Open Show Work

Question Attempts: Unlimited

SAVE FOR LATER

SUBMIT ANSWER

Homework Answers

Answer #1

a. Percentage-of-completion method

2020 2021 2022
Cumulative cost incurred till previous period $0 $2,615,800 $5,248,800
Contract cost incurred $2,615,800 $2,633,000 $2,041,200
Estimated cost to complete $3,764,200 $2,041,200 $0
Total cost to complete $6,380,000 $7,290,000 $7,290,000
% of completion 41% 72% 100%
Contract price $8,360,000 $8,360,000 $8,360,000
Cumulative revenue to be recognized $3,427,600 $6,019,200 $8,360,000
Revenue to be recognized for each year $3,427,600 $2,591,600 $2,340,800
Less: Cost incurred in each year $2,615,800 $2,633,000 $2,041,200
Gross profit/ (loss) during the year $811,800 -$41,400 $299,600

b. Completed-contract method

2020 2021 2022
Revenue recognized 0 0 $8,360,000
Gross profit (loss) 0 0 $1,070,000*

* $8,360,000 - $7,290,000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing...
On March 1, 2017, Pharoah Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,390,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 2017 2018 2019 Contract costs incurred during the year $3,003,300 $2,179,700 $2,117,000 Estimated costs to complete the contract at 12/31 3,386,700...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $40,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          18,000         28,000 Collections to date                     5,000           15,000         26,000 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is___________________________ .
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
During 2020, Blossom Company started a construction job with a contract price of $1,184,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,184,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $296,000 $610,500 $791,800 Estimated costs to complete 444,000 203,500 0 Billings to date (non-refundable) 222,000 666,000 1,184,000 Collections to date 199,800 599,400 1,054,500 (a) Partially correct answer iconYour answer is partially correct. Calculate the amount of gross profit to be recognized each year, assuming...
During 2020, Indigo Corporation started a construction job with a contract price of $5.46 million. Indigo...
During 2020, Indigo Corporation started a construction job with a contract price of $5.46 million. Indigo ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Indigo sends billings as revenues are earned. Billings are non-refundable. The following information is available Costs incurred to date 2020 : $780,000 2021: $2,730,000 2022: $5,360,000 Estimated costs to complete: 2020: $4,095,000 2021: $2,730,000 2022: $ -0- Required: Calculate...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of $5,820,000. Bramble estimated total construction costs would be $4,016,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date. $1,506,000 $2,652,000 $4,610,000 Estimated costs to complete. 2,510,000 1,768,000 -0- Customer billings to date 2,220,000 4,016,000 5,620,000 Collections to date 2,020,000 3,520,000 5,520,000 Fill in the...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract...
On May 1, 2017, Collin Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below. 2017 2018 2019 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0- Billings 1,200,000 4,100,000 4,300,000 Instructions(a) Using...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 (a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT