Question

On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...

On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction:

Date Expenditures

March 1, 2019 $ 1,200,000

May 1, 2019 1,680,000

August 1, 2019 3,000,000

September 30, 2019 4,800,000

The building was completed and ready for occupancy on September 30, 2019. To finance purchase of the land and construction of the building, $1,500,000 was borrowed on March 1, 2019 on a 9%, 3-year note payable. Other than the construction note, the only debt outstanding during 2019 was a $1,000,000, 12%, 6-year note payable dated January 1, 2019.

The interest cost to be capitalized during 2019 is

Homework Answers

Answer #1
Interest amount to be capitalised upto the completion of the project
Building completed date September 30 -2019
Hence interest upto 30th september can be capitalised
1st case Interest on $ 1500000 is
[(1500000 x 9% )/ 12 months ] x 7 months (from march to sep)
Which is $ 78750
2nd case Interest on [( 1000000 x 12% ) /12 months ] x 9 months (from january to sep )
Which is $ 90000
Total interest to be capitalised ( 78750+90000) $ 168750
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date                                                   Expenditures March 1, 2019                                  $   1,200,000 May 1, 2019                                          1,680,000 August 1, 2019                                      3,000,000 September 30, 2019                              4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
28. On March 1 Imhoff Co. began construction of a small building. Payments of 180,000 were...
28. On March 1 Imhoff Co. began construction of a small building. Payments of 180,000 were scheduled monthly for four months beginning March 1. The building was completed and ready for occupancy on June 1. In determining the amount of interest cost to be capitalized, the weighted-average accumulated expenditures are: A. 90,000.B. 180,000. C. 360,000.D. 720,000.
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 330,000 September 1, 2018 $ 495,000 December 31, 2018 $ 495,000 March 31, 2019 $ 495,000 September 30, 2019 $ 330,000 Dreamworld had $6,500,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 328,000 September 1, 2018 $ 486,000 December 31, 2018 $ 486,000 March 31, 2019 $ 486,000 September 30, 2019 $ 328,000 Dreamworld had $6,200,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 343,000 September 1, 2018 $ 501,000 December 31, 2018 $ 501,000 March 31, 2019 $ 501,000 September 30, 2019 $ 343,000 Dreamworld had $6,700,000 in 14% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
ABC Co. would like to construct a new office complex. On January 1, 2017 ABC Co....
ABC Co. would like to construct a new office complex. On January 1, 2017 ABC Co. borrowed $3,000,000 at 10% payable annually to finance the construction of the new complex. During 2017, ABC Co. made the following expenditures directly related to the construction project: April 1, $400,000 July 1, $1,800,000 October 1, $2,000,000 December 31, $1,000,000 The construction was completed in March, 2018. There were other debts outstanding during 2017 as follows: 10-year, 12% note payable, dated January 1, 2015....