Below is a chart outlining the activity cost pools for the Wheatley Corporation:
Job |
||||||
Activity |
Cost Driver |
Cost |
Total |
A |
B |
C |
Inspection |
# of inspections |
$50000 |
5623 |
X |
1989 |
1184 |
Delivery |
km driven |
$100000 |
45050 |
18974 |
Y |
8140 |
Setup |
# of setups |
$30000 |
10336 |
3000 |
1874 |
Z |
What are the missing numbers:
Select one:
a. X=4439, Y=26076, Z=5462
b. X=3634, Y=17936, Z=8462
c. X=9, Y=2, Z=3
d. X=2450, Y=17936, Z=5462
The correct answer is option (d)
It is explained as below
Activity |
Cost Driver |
Cost |
Total |
A |
B |
C |
Inspection |
No of inspections |
$50000 |
5623 |
2450 |
1989 |
1184 |
Delivery |
km driven |
$100000 |
45050 |
18974 |
17936 |
8140 |
Setup |
No of setups |
$30000 |
10336 |
3000 |
1874 |
5462 |
Working Notes
Total Job =A+B+C
A=Total Job-(B+C)
=5623-(1989+1184)
=2450
B= Total Job =A+B+C
= Total Job-(A+C)
=45050-(18974+8140)
=17936
C= Total Job =A+B+C
=Total Job-(A+B)
=10336-(3000+1874)
=5462