A company has identified the following overhead costs and cost drivers for the coming year: |
Budgeted | |||
Overhead Item | Cost Driver | Budgeted Cost | Activity Level |
Machine setup | Number of setups | $ 25,300 | 220 |
Inspection | Number of inspections | 124,200 | 4,600 |
Material handling | Number of material moves | 99,200 | 6,200 |
Engineering | Engineering hours | 12,400 | 620 |
Budgeted direct labor cost was $130,550 and budgeted direct material cost was $369,540. The following information was collected on three jobs that were completed during the year: |
Job 101 | Job 102 | Job 103 | |||
Direct materials | $ 5,250 | $ 10,250 | $ 6,250 | ||
Direct labor | $ 2,300 | $ 2,300 | $ 4,600 | ||
Units completed | 50 | 25 | 150 | ||
Number of setups | 1 | 2 | 2 | ||
Number of inspections | 10 | 5 | 15 | ||
Number of material moves | 15 | 5 | 40 | ||
Engineering hours | 5 | 25 | 8 |
If the company uses traditional costing and allocates overhead using direct labor cost, what is the cost of each unit of Job 102? |
$539.80.
$686.00.
$749.80.
$933.80.
Solution:
Total budgeted overhead cost = $25,300 + $124,200 + $99,200 + $12,400 = $261,100
Budgeted direct labor cost = $130,550
Overhead allocation rate based on direct labor cost = Budgeted overhead / Budgeted direct labor cost = $261,100 / $130,550 = $2 per direct labor dollar
Total cost of Job 102 = Direct material + Direct labor + Overhead applied
= $10,250 + $2,300 + ($2,300 *2) = $17,150
Nos of units in Job 102 = 25
Cost of each unit of Job 102 = $17,150 / 25 = $686 per unit
Hence 2nd option is correct.
Get Answers For Free
Most questions answered within 1 hours.