Question

Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year.

Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity
Ordering and Receiving Orders $   140000 500 orders
Machine Setup Setups 315000 450 setups
Machining Machine hours 1562500 125000 MH
Assembly Parts 1240000 1000000 parts
Inspection Inspections 320000

500 inspections

If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is

$0.14 per part.

$280 per order.

$1.40 per direct labor hour.

$7155 per order.

Homework Answers

Answer #1
Answer:
Overhead application rate for ordering and receiving based on activity-based costing
                  = Estimated overhead / Number of Orders
                  =   $ 140,000 / 500 Orders
                  =     $ 280 per Oder
Overhead application rate   =    $ 280 per Oder
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. Foxx Company incurs $410000 overhead costs each year in its three main departments, setup ($35000),...
1. Foxx Company incurs $410000 overhead costs each year in its three main departments, setup ($35000), machining ($265000), and packing ($110000). The setup department performs 40 setups per year, the machining department works 5000 hours per year, and the packing department packs 500 orders per year. Information about Foxx’s two products is as follows: Product A1 Product B1 Number of setups      20     20 Machining hours   1000 4000 Orders packed    150    350 Number of products manufactured    600    400 If machining hours...
Texas Co. established the following overhead cost pools and cost drivers: Budgeted Estimated Overhead Cost Pool...
Texas Co. established the following overhead cost pools and cost drivers: Budgeted Estimated Overhead Cost Pool Overhead Cost Driver Cost Driver Level Quality controls $780,000 # of inspections 26,000 inspections Machine setups $720,000 # of setups 12,000 setups Other overhead costs $900,000 # of machine hrs 50,000 machine hrs Total overhead costs $2,400,000 A recent order for sailboats used: Quality inspections 750 inspections Machine setups 500 setups Machine hours (MHs) 2,400 machine hours Required: a. What is the overhead rate...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $441,280 Number of setups 560 Ordering costs 318,600 Number of orders 17,700 Machine costs 890,400 Machine hours 42,400 Receiving 294,000 Receiving hours 8,400 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $611,000 $832,000 Direct labor $481,000 $473,000 Units completed 15,400 8,300...
Tiger Company has identified the following overhead costs and cost drivers for next year: Overhead Item...
Tiger Company has identified the following overhead costs and cost drivers for next year: Overhead Item Expected Costs Cost Driver Maximum Quantity Setup costs $583,200 Number of setups 2,400 Ordering costs 270,000 Number of orders 20,000 Maintenance 928,000 Machine-hours 32,000 Power 90,000 Kilowatt-hours 200,000 The following are two of the jobs completed during the year: Job 201 Job 202 Direct materials $9,000 $10,000 Direct labor $12,000 7,000 Units completed 750 600 Direct labor-hours 45 110 Number of setups 6 7...
Tiger Company has identified the following overhead costs and cost drivers for next year: Overhead Item...
Tiger Company has identified the following overhead costs and cost drivers for next year: Overhead Item Expected Costs Cost Driver Setup costs $583,200 Number of setups Ordering costs 270,000 Number of orders Maintenance 928,000 Machine-hours Power 90,000 Kilowatt-hours The following are two of the jobs completed during the year: Job 201 Job 202 Direct materials $9,000 $10,000 Direct labor $12,000 7,000 Units completed 750 600 Direct labor-hours 45 110 Number of setups 6 7 Number of orders 8 15 Machine-hours...
Wings Co. budgeted $569,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing...
Wings Co. budgeted $569,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level for Cost Driver Overhead Cost Driver Materials handling $ 184,000 4,600 pounds Weight of materials Machine setup 15,900 530 setups Number of setups Machine repair 1,200 30,000 machine hours Machine hours Inspections 21,000 300 inspections Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor 20 hours Direct materials 190...
The controller established the following overhead cost pools and cost drivers: Overhead Cost Pool Budgeted Overhead...
The controller established the following overhead cost pools and cost drivers: Overhead Cost Pool Budgeted Overhead Cost Driver Estimated Cost Driver Level Machine setups $207,000 # of setups 180 setups Material handling 138,000 # of pounds 12,000 Quality control 245,000 # of inspections 1,000 inspections Other overhead cost 220,000 # of machine hrs 20,000 machine hrs An order of steel tubing used the following amounts of the cost drivers: # of setups                               12 # of pounds                            700 # of inspections                      ...
Elevated Expectations Company projected the following overhead costs and cost drivers for past year (assume that...
Elevated Expectations Company projected the following overhead costs and cost drivers for past year (assume that actual overhead and budgeted overhead were the same): Overhead Item Expected Costs Cost Driver Expected Quantity Setup costs $12,150 Number of setups 50 Ordering costs 4,050 Number of orders 30 Maintenance 17,400 Machine-hours 600 Power 3,000 Kilowatt-hours 600 Direct Labor Hours 500 Elevated Expectations contracted for 2 jobs, both of which were completed during the year. Production managers reported the following data in relation...
A company has identified the following overhead costs and cost drivers for the coming year:     ...
A company has identified the following overhead costs and cost drivers for the coming year:               Budgeted   Overhead Item   Cost Driver Budgeted Cost    Activity Level   Machine setup   Number of setups $ 25,300           220           Inspection   Number of inspections 124,200         4,600           Material handling   Number of material moves 99,200         6,200           Engineering   Engineering hours 12,400         620                  Budgeted direct labor cost was $130,550 and budgeted direct material cost was $369,540. The following information was collected on...
10. Vertex Tires manufactures tires for dune buggies and has two different products, nubby tires and...
10. Vertex Tires manufactures tires for dune buggies and has two different products, nubby tires and smooth tires. The company produces 5,000 nubby tires and 10,000 smooth tires each year and incurs $167,000 of overhead costs. The following information is available:      Activity       Total Cost         Cost Driver   Materials handling $60,000       Number of requisitions Machine setups      50,000       Number of setups Quality inspections 57,000       Number of inspections For the nubby tires, the company has 400 requisitions, 200 setups, and 200...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT