Westerner Manufacturing has established the following cost pools for this year:
Cost Pool |
Costs |
Cost Drivers |
Maintenance |
$20,000 |
10,000 machine hours |
Material handling |
$25,000 |
250 moves |
Machine setup |
$30,000 |
1,000 hours |
Inspection |
$25,000 |
500 inspections |
Total |
$100,000 |
N/A |
The following information pertains to two representative jobs completed during January:
Item |
Job 101 |
Job 102 |
Direct materials |
$10,000 |
$7,500 |
Direct labor |
$8,000 |
$5,000 |
Units produced |
2,000 |
1,500 |
Direct labor hours |
640 |
400 |
Machine hours |
700 |
650 |
Number of material moves |
40 |
15 |
Number of setup hours |
80 |
40 |
Number of inspections |
35 |
15 |
11.5 Determine the cost driver rate under activity-based costing for each setup.