Determine over- and underbillings for a company with the following information Job Number: 20-318 Job Name:...

  1. Determine over- and underbillings for a company with the following information

Job Number: 20-318

Job Name: Mountain Peak Office Remodel

Current Contract Amount: $256,852

Total Estimated Cost at Completion: $225,236

Actual Costs to Date: $202,138

Total Billed: $252,253

Job Number: 20-319

Job Name: Market Street Warehouse

Current Contract Amount: $55,123

Total Estimated Cost at Completion: $45,224

Actual Costs to Date: $5,211

Total Billed: $5,500

Homework Answers

Answer #1
Job Number 20-318
Percentage Completion 89.74% =202138/225236
Revenue to be recognized 230,499 =256852*89.74%
Over Billing Amount $ 21,754 =252253-230499
( Actual Billing - Revenue to be recognized )
Job Number 20-319
Percentage Completion 11.52% =5211/45224
Revenue to be recognized        6,350 =55123*11.52%
Under Billing Amount $ 1,139 =6350-5211
( Revenue to be recognized - Actual Billing )
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant...
1.Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job...
During 2019, Almon Inc. started a construction job with a contract price of $8000. The job was completed in 2019 and information for the three years of construction is as follows: 2019 2020 2021 TOTAL costs incurred to date (ie sum of all costs, for all years, incurred at the end of the year) $2,000 $4,500 $7,600 Estimated costs to complete (as estimated at year end) 5,000 2900 -0- Billings to date 2,200 6,000 8,000 Collections to date 1,600 4,800...
During 2020, Blossom Company started a construction job with a contract price of $1,184,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,184,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $296,000 $610,500 $791,800 Estimated costs to complete 444,000 203,500 0 Billings to date (non-refundable) 222,000 666,000 1,184,000 Collections to date 199,800 599,400 1,054,500 (a) Partially correct answer iconYour answer is partially correct. Calculate the amount of gross profit to be recognized each year, assuming...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Problema IV (20 Puntos) Guaraguao Manufacturing is a small manufacturer that uses machine-hours as its activity...
Problema IV (20 Puntos) Guaraguao Manufacturing is a small manufacturer that uses machine-hours as its activity base for assigned overhead costs to jobs. The company estimated the following amounts for 2018 for the company and for Job 62:                                                                    Company                 Job 325                                                                   Estimasted                                                                   Annual Cost              Direct materials                                    $70,000                   $5,500 Direct labor                                           $30,000                   $2,300 Manufacturing overhead costs             $67,500 Machine hours                                        90,000                     2,000 During 2018, the actual machine-hours totaled 94,000, and actual manufacturing overhead costs were $72,000. Instructions: Compute the predetermined overhead rate. Compute the total manufacturing costs for Job 325....
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost...
Current Attempt in Progress A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job:        Direct materials        Direct labor         Manufacturing overhead      Total cost      Unit cost (1) What are the source documents for direct materials, direct labor, and...
1. A job order cost sheet for Sheridan Company is as follows. Job No. 92 For...
1. A job order cost sheet for Sheridan Company is as follows. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,500 7,400 5,920 8 7,400 12 8,400 6,888 25 2,900 27 4,400 3,608 16,800 20,200 16,416 Cost of completed job:    Direct materials $16,800    Direct labor 20,200    Manufacturing overhead 16,416 Total cost $53,416 Unit cost ($53,416 ÷ 2,000) $26.71 On the basis of this data, answer the following questions. (a) What was...
A company has the following information for Job Alpha during July: Units produced              257 Actual...
A company has the following information for Job Alpha during July: Units produced              257 Actual materials used           1,722 lbs. Actual materials cost $         5.85 per lb. Actual labor hours incurred              771 Actual labor rate $      14.25 per hour Work in process, July 1 $      4,000 Work in process, July 31 $             -   The company applies manufacturing overhead to jobs based on direct labor hours. Additional information for the company in July is as follows: Total estimated labor...
Terminus Company completed two jobs during January, Job Z-15 and Job W-20. Completing Job Z-15 required...
Terminus Company completed two jobs during January, Job Z-15 and Job W-20. Completing Job Z-15 required an additional $2,720 in direct labour and completing Job W-20 required $1,296 in direct materials and $8,000 in direct labour. The details of the two jobs in process on January 1 are as follows: Job Z-15 Job W-20 Direct Materials $ 2,038 $ 1,280 Direct Labour 768 3,360 On January 1 the Materials Inventory balance was $11,040, and $1,392 worth of materials was purchased...