Question

Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,523 tons...

Equivalent Units of Conversion Costs

The Rolling Department of Oak Ridge Steel Company had 6,523 tons in beginning work in process inventory (10% complete) on July 1. During July, 59,300 tons were completed. The ending work in process inventory on July 31 was 4,744 tons (60% complete).

What are the total equivalent units for conversion costs? Round to the nearest whole unit.

Homework Answers

Answer #1

Solution:

Using Weighted Aveareg method:

Units % Conversion EUP- Conversion
Units Completed and transferred out 59300 100% 59300
units of Ending work in process 4744 60% 2846
Equivalent units of production 62146

Using FIFO method:

Units % Conversion EUP- Conversion
units in process, July 1 6523 90% 5871
Units started and completed during July (59300-6523) 52777 100% 52777
Toal units completed and transferred out 58648
Units in process, July 31 4744 60% 2846
Equivalent units of production 61494

Note: Since method is not provided. I have solved by both method. You may refer the method which you may need.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,200 tons...
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,200 tons in beginning work in process inventory (60% complete) on July 1. During July, 52,500 tons were completed. The ending work in process inventory on July 31 was 2,600 tons (30% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 10,800 tons...
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 10,800 tons in beginning work in process inventory (30% complete) on July 1. During July, 67,800 tons were completed. The ending work in process inventory on July 31 was 3,400 tons (70% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 7,011 tons in...
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 7,011 tons in beginning work in process inventory (50% complete) on October 1. During October, 77,900 tons were completed. The ending work in process inventory on October 31 was 4,674 tons (80% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. units =
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 4,433 tons in...
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 4,433 tons in beginning work in process inventory (80% complete) on October 1. During October, 34,100 tons were completed. The ending work in process inventory on October 31 was 2,046 tons (90% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit.
The Rolling Department of Kraus Steel Company had 6,446 tons in beginning work in process inventory...
The Rolling Department of Kraus Steel Company had 6,446 tons in beginning work in process inventory (50% complete) on October 1. During October, 58,600 tons were completed. The ending work in process inventory on October 31 was 5,274 tons (20% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. units
The Rolling Department of Kraus Steel Company had 1,962 tons in beginning work in process inventory...
The Rolling Department of Kraus Steel Company had 1,962 tons in beginning work in process inventory (10% complete) on October 1. During October, 32,700 tons were completed. The ending work in process inventory on October 31 was 2,616 tons (70% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit.
1. The Rolling Department of Kraus Steel Company had 2,442 tons in beginning work in process...
1. The Rolling Department of Kraus Steel Company had 2,442 tons in beginning work in process inventory (20% complete) on October 1. During October, 40,700 tons were completed. The ending work in process inventory on October 31 was 3,663 tons (20% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. ______units 2. The cost of direct materials transferred into the Rolling Department of Kraus Company is $518,400. The conversion cost for the period...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 11,900 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 11,900 tons in beginning work in process inventory (40% complete) on October 1. During October, 74,200 tons were completed. The ending work in process inventory on October 31 was 3,700 tons (60% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? _______units
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,700 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,700 tons in beginning work in process inventory (90% complete) on October 1. During October, 60,900 tons were completed. The ending work in process inventory on October 31 was 3,000 tons (70% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? units Feedback Are you determining the equivalent units of materials added or of...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 2,400 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 2,400 tons in beginning work in process inventory (40% complete) on October 1. During October, 39,500 tons were completed. The ending work in process inventory on October 31 was 2,000 tons (30% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process?