Equivalent Units of Materials Cost
The Rolling Department of Oak Ridge Steel Company had 10,800 tons in beginning work in process inventory (30% complete) on July 1. During July, 67,800 tons were completed. The ending work in process inventory on July 31 was 3,400 tons (70% complete).
What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Equivalent Units of material 71,200
Working:
UNITS |
Material Cost |
Conversion |
|||||
% Completion |
Units |
% Completion |
Units |
||||
Units started and completed |
67,800 |
100% |
67,800 |
100% |
44,400 |
||
Ending Work in Process |
3,400 |
100% |
3,400 |
70% |
2,380 |
||
Total Equivalent units |
71,200 |
71,200 |
46,780 |
Equivalent units of material is 71,200 units
Note:
Note: As no method describes, weighted average method has been applied