Question

Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 10,800 tons...

Equivalent Units of Materials Cost

The Rolling Department of Oak Ridge Steel Company had 10,800 tons in beginning work in process inventory (30% complete) on July 1. During July, 67,800 tons were completed. The ending work in process inventory on July 31 was 3,400 tons (70% complete).

What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?

Homework Answers

Answer #1

Equivalent Units of material 71,200

Working:

UNITS

Material Cost

Conversion

% Completion

Units

% Completion

Units

Units started and completed

67,800

100%

67,800

100%

44,400

Ending Work in Process

3,400

100%

3,400

70%

2,380

Total Equivalent units

71,200

71,200

46,780

Equivalent units of material is 71,200 units

Note:

Note: As no method describes, weighted average method has been applied

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,200 tons...
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,200 tons in beginning work in process inventory (60% complete) on July 1. During July, 52,500 tons were completed. The ending work in process inventory on July 31 was 2,600 tons (30% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,523 tons...
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,523 tons in beginning work in process inventory (10% complete) on July 1. During July, 59,300 tons were completed. The ending work in process inventory on July 31 was 4,744 tons (60% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit.
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 2,400 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 2,400 tons in beginning work in process inventory (40% complete) on October 1. During October, 39,500 tons were completed. The ending work in process inventory on October 31 was 2,000 tons (30% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process?
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 6,200 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 6,200 tons in beginning work in process inventory (40% complete) on October 1. During October, 38,700 tons were completed. The ending work in process inventory on October 31 was 1,900 tons (20% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? _____ units
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,100 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,100 tons in beginning work in process inventory (90% complete) on October 1. During October, 51,400 tons were completed. The ending work in process inventory on October 31 was 2,600 tons (80% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? units
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 11,900 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 11,900 tons in beginning work in process inventory (40% complete) on October 1. During October, 74,200 tons were completed. The ending work in process inventory on October 31 was 3,700 tons (60% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? _______units
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,700 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,700 tons in beginning work in process inventory (90% complete) on October 1. During October, 60,900 tons were completed. The ending work in process inventory on October 31 was 3,000 tons (70% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? units Feedback Are you determining the equivalent units of materials added or of...
The Rolling Department of Kraus Steel Company had 3,600 tons in beginning work in process inventory...
The Rolling Department of Kraus Steel Company had 3,600 tons in beginning work in process inventory (60% complete) on October 1. During October, 59,900 tons were completed. The ending work in process inventory on October 31 was 3,000 tons (30% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process?
The Rolling Department of Kraus Steel Company had 200 tons in beginning work in process inventory...
The Rolling Department of Kraus Steel Company had 200 tons in beginning work in process inventory (60% complete) on October 1. During October, 3,900 tons were completed. The ending work in process inventory on October 31 was 300 tons (25% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process?
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 7,011 tons in...
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 7,011 tons in beginning work in process inventory (50% complete) on October 1. During October, 77,900 tons were completed. The ending work in process inventory on October 31 was 4,674 tons (80% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. units =