Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,200 tons in beginning work in process inventory (60% complete) on July 1. During July, 52,500 tons were completed. The ending work in process inventory on July 31 was 2,600 tons (30% complete).
What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Solution
Equivalent units for material = 55,100
Working
Statement of Equivalent Units(Weighted average) | |||||||
Material | |||||||
Units | Complete % | Equivalent units | |||||
Transferred out | 52,500 | 100% | 52,500 | ||||
Ending WIP | 2,600 | 100% | 2,600 | ||||
Total | 55,100 | Total | 55,100 |