Question

Ship-Builders Co. began construction of a new cutter for the U.S. Coast Guard on January 1,...

Ship-Builders Co. began construction of a new cutter for the U.S. Coast Guard on January 1, 2018 and completed construction of the ship on March 31, 2019. To help finance construction, Ship-Builders took out an $8,000,000, 2-year, 7% loan on January 1, 2018. Interest on the loan was to be paid annually at the end of each year and the principal at the end. Ship-Builders has no other outstanding interest-bearing debt. Ship-Builders made the following expenditures in conjunction with this construction project:

Date

Amount

2/1/2018

$

1,200,000

3/1/2018

650,000

4/1/2018

600,000

8/1/2018

1,100,000

10/1/2018

700,000

11/1/2018

800,000

3/1/2019

2,500,000

How much interest should Ship-Builders Co. capitalize in 2018? How much should they expense in 2018?

Homework Answers

Answer #1

As per Accounting standards of borrowing cost, if an loan or debt taken specifically for funding of qualifying assest then amount of interest capitalised should be actual cost incurred less any income earned by temporary investment of these funds related to that loan or debt.

In present case, loan of $ 80,00,000 taken specifically for construction of the ship.Hence whole interest cost should be capitalise by ship builders co.and not any cost should be expensed off in 2018.

Total cost to be capitalise= $ 80,00,000*7%*1 year = $560000

Total interest to be expensed off =NIL

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,820,000 March 1, 2018 1,440,000 June 30, 2018 1,640,000 October 1, 2018 1,440,000 January 31, 2019 396,000 April 30, 2019 729,000 August 31, 2019 1,026,000 On January 1, 2018, the company obtained a $4,400,000 construction loan with a 14% interest rate....
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, ABC Company began construction of a building to be used as its...
On January 1, 2018, ABC Company began construction of a building to be used as its warehouse. The building was completed on November 1, 2019. Expenditures for the project during 2018 were as follows: January 1, 2018 900,000 April 1, 2018 700,000 July 1, 2018 650,000 October 1, 2018 840,000 On January 1, 2018, ABC Company obtained a $4,000,000 construction loan with 9% interest rate payable in 5 years. The Company’s other debts included a note of $1,000,000 at 11%...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 330,000 September 1, 2018 $ 495,000 December 31, 2018 $ 495,000 March 31, 2019 $ 495,000 September 30, 2019 $ 330,000 Dreamworld had $6,500,000 in 12% bonds outstanding through both years. The average accumulated expenditures for 2019 by the end of the construction period was:
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be used as its office headquarters. The building was completed on June 30, 2019. Expenditures on the project, mainly payments to subcontractors, were as follows: January 1, 2018 $500,000 March 31, 2018 $400,000 September 30, 2018 $600,000 Accumulated expenditures at December 31, 2018 $1,500,000 (before interest capitalization) January 31, 2019 $600,000 April 30, 2019 $300,000 On January 1, 2018, the company obtained a $1,000,000 construction...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $11,500,000 and an effective interest rate of 10%. Construction expenditures incurred during 2018 were as follows: January 1 $ 650,000 March 1 690,000 July 31 570,000 September 30 750,000 December 31 450,000 Date Expenditure Weight Average January 1...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 328,000 September 1, 2018 $ 486,000 December 31, 2018 $ 486,000 March 31, 2019 $ 486,000 September 30, 2019 $ 328,000 Dreamworld had $6,200,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 343,000 September 1, 2018 $ 501,000 December 31, 2018 $ 501,000 March 31, 2019 $ 501,000 September 30, 2019 $ 343,000 Dreamworld had $6,700,000 in 14% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,350,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 14% bonds $3,000,000, 9% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 960,000 March 31 1,560,000 June 30 1,232,000 September 30 960,000...