Question

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows:

January 1, 2018 $ 1,820,000

March 1, 2018 1,440,000

June 30, 2018 1,640,000

October 1, 2018 1,440,000

January 31, 2019 396,000

April 30, 2019 729,000

August 31, 2019 1,026,000

On January 1, 2018, the company obtained a $4,400,000 construction loan with a 14% interest rate. The loan was outstanding all of 2018 and 2019. The company’s other interest-bearing debt included two long-term notes of $2,000,000 and $8,000,000 with interest rates of 10% and 12%, respectively. Both notes were outstanding during all of 2018 and 2019. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required: 1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the specific interest method.

2. What is the total cost of the building?

3. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows:   January 1, 2016 $ 1,000,000   March 1, 2016 800,000   June 30, 2016 1,500,000   October 1, 2016 1,000,000   January 31, 2017 300,000   April 30, 2017 600,000   August 31, 2017 900,000 On January 1, 2016, the company obtained a $8.000,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be...
On January 1, 2018, the Mills Conveying Equipment Company began construction of a building to be used as its office headquarters. The building was completed on June 30, 2019. Expenditures on the project, mainly payments to subcontractors, were as follows: January 1, 2018 $500,000 March 31, 2018 $400,000 September 30, 2018 $600,000 Accumulated expenditures at December 31, 2018 $1,500,000 (before interest capitalization) January 31, 2019 $600,000 April 30, 2019 $300,000 On January 1, 2018, the company obtained a $1,000,000 construction...
On January 1, 2018, ABC Company began construction of a building to be used as its...
On January 1, 2018, ABC Company began construction of a building to be used as its warehouse. The building was completed on November 1, 2019. Expenditures for the project during 2018 were as follows: January 1, 2018 900,000 April 1, 2018 700,000 July 1, 2018 650,000 October 1, 2018 840,000 On January 1, 2018, ABC Company obtained a $4,000,000 construction loan with 9% interest rate payable in 5 years. The Company’s other debts included a note of $1,000,000 at 11%...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,050,000 at 11% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $6,000,000, 16% bonds $4,000,000, 11% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 840,000 March 31 1,440,000 June 30 1,088,000 September 30 840,000...
On January 1, 2018, the Marjlee Company began construction of an office building to be used...
On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $6,000,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 14% $ 1,500,000 Long-term note, 13% 2,000,000 Long-term note, 10% 4,000,000 Required: Calculate the amount of interest capitalized in 2018 for the building using the...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2019 (assuming interest...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2018, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 300,000 September 1, 2018 $ 450,000 December 31, 2018 $ 450,000 March 31, 2019 $ 450,000 Dreamworld had the following debt obligations outstanding during both years: Construction loan, 10%             $500,000              Long-term note, 12%                      $2,500,000 Required: What would Dreamworld's capitalized interest be in 2018? $45,000 $134,000...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,350,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 14% bonds $3,000,000, 9% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 960,000 March 31 1,560,000 June 30 1,232,000 September 30 960,000...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Shagri Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The only interest-bearing debt the company had outstanding during 2018 was long-term bonds with a book value of $11,500,000 and an effective interest rate of 10%. Construction expenditures incurred during 2018 were as follows: January 1 $ 650,000 March 1 690,000 July 31 570,000 September 30 750,000 December 31 450,000 Date Expenditure Weight Average January 1...
Ship-Builders Co. began construction of a new cutter for the U.S. Coast Guard on January 1,...
Ship-Builders Co. began construction of a new cutter for the U.S. Coast Guard on January 1, 2018 and completed construction of the ship on March 31, 2019. To help finance construction, Ship-Builders took out an $8,000,000, 2-year, 7% loan on January 1, 2018. Interest on the loan was to be paid annually at the end of each year and the principal at the end. Ship-Builders has no other outstanding interest-bearing debt. Ship-Builders made the following expenditures in conjunction with this...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT