Consider the following information: Project Boom (50%) Recession (50%) A $20 -$10 B -$10 $20 C $30 $-30 D $50 $50
What is the expected value and variance of project A.
The following table is required for expected value (E) and variance (V).
Project A
X |
F |
E = X × F |
X^2 |
FX^2 |
|
Boom |
20 |
0.5 |
10 |
20^2 = 400 |
0.5 × 400 = 200 |
Recession |
-10 |
0.5 |
-5 |
-10^2 = 100 |
0.5 × 100 = 50 |
Total |
1 |
5 |
250 |
Answer: the expected value is $5.
Variance = (FX^2 / F) – E^2
= (250 / 1) – 5^2
= 250 – 25
= $225 (Answer)