Question

A contractor estimates the probabilities for the number of weeks required to complete a certain type...

A contractor estimates the probabilities for the number of weeks required to complete a certain type of construction project which takes 11 to 15 weeks to complete as follows:

Completion Time (Weeks)

11

12

13

14

15

Probability

X

0.25

0.35

0.10

X

Find X.

Select one:

a. 0.20

b. 0.30

c. Cannot be determined from the information given

d. 0.15

Homework Answers

Answer #1

The given probability distribution table is:

Completion time weeks

11

12

13

14

15

Probability

X

0.25

0.35

0.10

X

Let ‘X’ be the missing values.

Assume P(11) = P(12) = X.

Find the missing value of X by using the condition that the total of all the probabilities equal 1.

P( 11 ) + P(12) + P(13) + P(14) + P(15) = 1

X + 0.25 + 0.35 + 0.10 + X = 1

2X+ 0.70 = 1

2X = 1 – 0.70

2X= 0.30

X = 0.30/2

X = 0.15

Thus, the complete probability distribution table is,

Completion time weeks

11

12

13

14

15

Probability

0.15

0.25

0.35

0.10

0.15

Since sum of all probabilities corresponding to completion time of each week is equal to 1, so the value of X is 0.15

Therefore, the correct option is d. 0.15.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
9. A contractor estimates the probabilities for the number of days required to complete a certain...
9. A contractor estimates the probabilities for the number of days required to complete a certain type of construction project as follows: Table 1: Distribution of days of completion Time (Days) 1 2 3 4 5 Probability 0.05 0.20 0.35 0.30 0.10 (a) What is the probability a randomly chosen project will take less than 3 days to complete? (b) Find the expected time to complete. (c) Find the variance of time required to complete a project. (d) The contractor’s...
(All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities...
(All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.25 6 0.35 7 0.25 8 0.15 B 3 0.20 5 0.55 7 0.25 C 10 0.10 12 0.25 14 0.40 16 0.20 18 0.05 D 8 0.60 10 0.40 (a)...
A statistician investigating the relationship between the amount of precipitation (in inches) and the number of...
A statistician investigating the relationship between the amount of precipitation (in inches) and the number of automobile accidents gathered data for 10 randomly selected days. The results: Day 1 2 3 4 5 6 7 8 9 10 Precipitation(X) 0.05 0.12 0.05 0.08 0.10 0.35 0.15 0.30 0.10 0.20 Number of Accidents(Y) 5 6 2 4 8 14 7 13 7 10 You have calculated some of the necessary summary information to carry out the analyses as follows: Compute the...
3. The Dynaco Manufacturing Company produces a product in a process consisting of operations of five...
3. The Dynaco Manufacturing Company produces a product in a process consisting of operations of five machines. The probability distribution of the number of machines that will break down in a week follows: Machine Breakdowns Per Week   Probability 0 0.10 1 0.20 2 0.15 3 0.30 4 0.15 5 0.10 1.00 a. Simulate the machine breakdowns per week for 20 weeks. b. Compute the average number of machines that will break down per week. 4. Simulate the following decision situation...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
7. Between Z=0 and Z=-3 a. 0.9987 b. -0.4987 c. 0.5000 d. 0.4987 e. 0.0013 8....
7. Between Z=0 and Z=-3 a. 0.9987 b. -0.4987 c. 0.5000 d. 0.4987 e. 0.0013 8. Between Z=-1.95 and Z=1.95 a. 0.9988 b. -0.4488 c. 0.4488 d. 0.9488 e. -0.9488 9. Between Z=1 and Z=3 a. 0.9987 b. 0.1573 c. 0.0013 d. 0.8413 e. 2 10. Find the Z value that corresponds to the given area . a. 1 b. 0.1 c. 0 d. 0.50 e. None of them 11. a. 0.8416 b. -0.1584 c. -0.20 d. -0.8416 e. 0.80...
1. Complete the PDF. x P(X = x) x · P(X = x) 0 0.1 1...
1. Complete the PDF. x P(X = x) x · P(X = x) 0 0.1 1 0.4 2 3 0.2 Part (a) Find the probability that X = 2. Part (b) Find the expected value. 2. A school newspaper reporter decides to randomly survey 16 students to see if they will attend Tet (Vietnamese New Year) festivities this year. Based on past years, she knows that 21% of students attend Tet festivities. We are interested in the number of students...
1. Let A denote the event that a particular stock outperforms the market and let B...
1. Let A denote the event that a particular stock outperforms the market and let B denote the event that the economy is experiencing rapid economic growth. Suppose that P(A) = 0.40, P(B) = 0.50 and P(A/B) is 0.20. Therefore, the two events A and B are probabilistically independent. True False 2. A manager estimates that demand for their company's product will increase within the next 2 quarters with probability 0.55. This is an example of a a. objective probability...
Code GEL ASX All Ordinary change% 2016/12/30 22.09 5719.1 2017/1/2 22.09 5719.1 0.00% 2017/1/3 22.51 5784.6...
Code GEL ASX All Ordinary change% 2016/12/30 22.09 5719.1 2017/1/2 22.09 5719.1 0.00% 2017/1/3 22.51 5784.6 1.15% 2017/1/4 22.32 5788.2 0.06% 2017/1/5 22.37 5805.1 0.29% 2017/1/6 22.21 5809 0.07% 2017/1/9 22.38 5857.7 0.84% 2017/1/10 22.16 5813 -0.76% 2017/1/11 22.14 5823.7 0.18% 2017/1/12 21.98 5821.6 -0.04% 2017/1/13 22.03 5776.8 -0.77% 2017/1/16 22.18 5803 0.45% 2017/1/17 22.17 5754.7 -0.83% 2017/1/18 22.24 5733.7 -0.36% 2017/1/19 22.55 5745.4 0.20% 2017/1/20 22.77 5709.7 -0.62% 2017/1/23 22.33 5668 -0.73% 2017/1/24 22.41 5706.3 0.68% 2017/1/25 22.24 5726...
Answer the question. CHAPTER 8: ESTIMATION AND CONFIDENCE INTERVALS 1. As degrees of freedom increase, the...
Answer the question. CHAPTER 8: ESTIMATION AND CONFIDENCE INTERVALS 1. As degrees of freedom increase, the t-distribution approaches the: A. binomial distribution B. exponential distribution C. standard normal distribution D. None of the above 2. Given a t-distribution with 14 degrees of freedom, the area left of - 1.761 is A. 0.025 B. 0.05 C. 0.10 D. 0.90 E. None of the above 3. 100 samples of size fifty were taken from a population with population mean 72. The sample...