The project manager of a task force planning the construction of
a domed stadium had hoped to be able to complete construction prior
to the start of the next college football season. After reviewing
construction time estimates, it now appears that a certain amount
of crashing will be needed to ensure project completion before the
season opener. Given the following time and cost estimates,
determine a minimum-cost crashing schedule that will shave five
weeks off the project length. Note: No activity can be
crashed more than two weeks.
CRASHING COSTS | |||||||
Activity | Immediate Predecessor | Normal Time (weeks) | First Week | Second Week | |||
A | — | 12 | $15,000 | $20,000 | |||
B | A | 14 | 10,000 | 10,000 | |||
C | — | 10 | 5,000 | 5,000 | |||
D | C | 17 | 20,000 | 21,000 | |||
E | C | 18 | 16,000 | 18,000 | |||
F | C | 12 | 12,000 | 15,000 | |||
G | D | 15 | 24,000 | 24,000 | |||
H | E | 8 | — | — | |||
I | F | 7 | 30,000 | — | |||
J | I | 12 | 25,000 | 25,000 | |||
K | B | 9 | 10,000 | 10,000 | |||
M | G | 3 | — | — | |||
N | H | 11 | 40,000 | — | |||
P | H, J | 8 | 20,000 | 20,000 | |||
End | K, M, N, P | ||||||
Crash schedule: (1 week each)
Week 1 | Week 2 | Week 3 | Week 4 | Week 5 |
(Click to select) C E F E and P P | (Click to select) E E and P P C F | (Click to select) P E and P E F C | (Click to select) C E and P F E P | (Click to select) E E and P P F C |
Length after crashing N weeks
Path | N=0 | 1 | 2 | 3 | 4 | 5 |
A-B-K | 35 | |||||
C-E-H-P | 44 | 43 | 42 | 42 | 42 | 40 |
C-D-G-M | 45 | 44 | 43 | 43 | ||
C-E-H-N | 47 | 46 | 45 | 45 | 45 | 44 |
C-F-I-J-P | 49 | 48 | 47 | 46 | 45 | 44 |
N=0 | 1 | 2 | 3 | 4 | 5 | |
Activity Crashed | C | C | F | F | E,P | |
Crashing Cost | 5000 | 5000 | 12000 | 15000 | 36000 | |
Total Cumulative cost | 5000 | 10000 | 22,000 | 37,000 | 73,000 |
Hence, Crash schedule is as follows:
Week 1 - Activity C
Week 2 - Activity C
Week 3 - Activity F
Week 4 - Activity F
Week 5 - Activity E,P
Get Answers For Free
Most questions answered within 1 hours.