Question

There are 3 servers: A, B, and C. They occasionally crash, independent of each other. Each...

There are 3 servers: A, B, and C. They occasionally crash, independent of each other. Each week server A has a 9% chance of crashing, server B has a 12% chance of crashing, and server C has a 14% chance of crashing.

What is the probability that:

1.) There are no crashes this week?

2.) There is exactly one crash this week?

3.) There are one or more crashes this week?

Homework Answers

Answer #1

a)

P(No crash) = P(A) * P(no crash) + P(B) * P(no crash) + P(C) * P(no crash)

= 1/ 3 * (1 - 0.09) + 1 / 3 * ( 1 - 0.12) + 1/3 ( 1 - 0.14)

= 0.8833

b)

P(Exactly one crash) = P(A) * P(crash) + P(B) * P(no crash) + P(C) * P(no crash) +

P(A) * P(no crash) + P(B) * P(crash) + P(C) * P(no crash) + P(A) * P(no crash) + P(C) * P(no crash) + P(C) * P(no crash)

= 1/ 3 * (0.09) + 1 / 3 * ( 1 - 0.12) + 1/3 ( 1 - 0.14) +1/ 3 * (1 - 0.09) + 1 / 3 * (0.12) + 1/3 ( 1 - 0.14)

+1/ 3 * (1 - 0.09) + 1 / 3 * ( 1 - 0.12) + 1/3 ( 0.14)

= 0.9664

c)

P( one or more crashes) = 1 - P( no crash)

= 1 - 0.8833

= 0.1167

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are distributing 1000 jobs to 7 servers (we are only interested in how many jobs...
You are distributing 1000 jobs to 7 servers (we are only interested in how many jobs each server gets). You pick a distribution uniformly at random. (a) What is the probability that server #1 gets at least 300 jobs? (b) What is the probability that there is at least one server that gets at least 300 jobs? (c) What is the probability that there is no server that gets at least 300 jobs? Discrete Math II (d) Assume server #1...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
7. Events A and B are independent. The P(A) = 3/5, P(not B) = 2/3. What...
7. Events A and B are independent. The P(A) = 3/5, P(not B) = 2/3. What is P(A and B)? a. 2/5 b. 1/5 c. 4/15 d. 2/15 8. A bag contains 4 red marbles, 3 blue marbles, and 7 green marbles. If a marble is randomly selected from the bag, what is the probability that it is blue? A) 1/11 B) 3/14 C) 1/7 D) 1/3 9. The distribution of the heights of students in a large class is...
According to TECH.CO, there are seven most common smartphone issues and there are simple fixes for...
According to TECH.CO, there are seven most common smartphone issues and there are simple fixes for most of them. One of the problems are phone crashes which accounted for approximately 25% of the performance issues.† Suppose that smartphones are shipped in lots of N = 60 phones. Before shipment, n = 9 phones are selected from a lot of N = 60 phones that contains M = 14 phones that will crash when tested. If there are no crashes among...
A computer server manufacturer currently has capacity and demand of 10,000 servers per year. It is...
A computer server manufacturer currently has capacity and demand of 10,000 servers per year. It is considering two options to increase its capacity. The first option is to add 10,000 units of capacity to the plant, this will incur an annualized (need to pay in each period) fixed cost of 10,000,000 plus 500 labor cost per server. The second option is to outsource the production (anything above the capacity) to an independent manufacturer at a cost of 2,000 for each...
A slot machine has 3 wheels; each wheel has 20 symbols; the three wheels are independent...
A slot machine has 3 wheels; each wheel has 20 symbols; the three wheels are independent of each other. Suppose that the middle wheel has 11 cherries among its 20 symbols, and the left and right wheels have 2 cherries each. a. You win the jackpot if all three wheels show cherries. What is the probability of winning the jackpot? b. What is the probability that the wheels stop with exactly 2 cherries showing among them?
Each day in April, you have an independent 1/4 chance of deciding to take a 6am...
Each day in April, you have an independent 1/4 chance of deciding to take a 6am run. (a) What is the probability you go on exactly 12 runs in the month of April (which has 30 days)? (b) What is the expected number of days you go running during April? (c) What is the probability that you go running at least once during April 1–7? (d) What is the probability that that your first run of the month occurs on...
1)Today, the waves are crashing onto the beach every 5.6 seconds. The times from when a...
1)Today, the waves are crashing onto the beach every 5.6 seconds. The times from when a person arrives at the shoreline until a crashing wave is observed follows a Uniform distribution from 0 to 5.6 seconds. Round to 4 decimal places where possible. a. The mean of this distribution is b. The standard deviation is   c. The probability that wave will crash onto the beach exactly 0.4 seconds after the person arrives is P(x = 0.4) =   d. The probability...
The project manager of a task force planning the construction of a domed stadium had hoped...
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT