General Construction, Inc., substantially performs its contract with Harry. If General Construction does not complete performance, it must
a. find a subcontractor to complete performance.
b. forfeit to Harry the entire price of the contract.
c. pay Harry the difference between substantial and complete performance.
d. do nothing more.
For any help regarding the answer, please write in the comments section and I will get back to it as soon as possible. Do give a positive rating if the answer helped you.
General Construction, Inc., substantially performs its contract with Harry. If General Construction does not complete performance, it must pay to harry the difference between substantial and complete performance. As substantial performance refers to incomplete work but meets all the standards of the contract With adequate performance.
Hence the correct option is (C) Pay Harry the difference between substantial and complete performance.